' City of Everett 00 7200- 18 <br /> Diversion Dam Road Phase 3 UT 3707 & UT 3708 <br /> Extensions of Contract Time will be granted only as provided in the General Conditions and to <br /> ' the extent that affected critical activities exceed the Total Float time along the affected paths of <br /> the reviewed Preliminary Schedule at the time the change was authorized in writing by the <br /> Owner. Contractor has the burden of clearly and convincingly demonstrating entitlement to any <br /> ' adjustment of Contract Time. <br /> If the Owner is solely responsible for any Delay to Substantial Completion, Physical Completion, <br /> Completion Date, or Final Acceptance, the Contractor shall only be entitled to compensation or <br /> other damages as described in 12.4 REMEDIES, provided that Contractor timely gave Notice <br /> pursuant to ARTICLE 10. NOTICE TO OWNER, timely submitted a Contract Claim pursuant to <br /> ARTICLE 12. CONTRACT CLAIMS and fulfilled the requirements of 5.2.2. Construction <br /> Schedule. <br /> 5.2.3. Construction Progress <br /> The Contractor shall furnish all labor, materials, facilities and Equipment necessary to insure the <br /> prosecution and completion of the Project within the interim milestones, Substantial Completion, <br /> Physical Completion and Completion Dates of the Contract. If Work falls seven (7) days or <br /> more behind the reviewed Preliminary Schedule, the Contractor agrees that, at its sole cost and <br /> ' expense, it will take all actions necessary to return the Project to the accepted schedule. These <br /> actions may include the following: <br /> 1. Increase labor in quantities and crafts. <br /> U <br /> 2. Increase the number of working hours per shift, shifts per working day, working days per <br /> week, or the amount of Equipment, or any combination of the foregoing. <br /> ' 3. Reschedule activities. <br /> If requested by the Owner's Representative, the Contractor shall prepare a proposed schedule <br /> revision demonstrating a plan to make up the lag in progress and insure completion of the Work <br /> ' within the Contract Time. All actions taken to return the Project to the accepted schedule are at <br /> the Contractor's expense. <br /> The Contractor shall pay all costs incurred by the Owner that result from the Contractor's action <br /> ' to return the Project to its accepted schedule, including, but not limited to, additional, overtime, <br /> or third party inspection, design and construction management service costs. Contractor agrees <br /> that Owner shall deduct such charges from payments due the Contractor. It is further <br /> understood and agreed that none of the services performed by the Owner's Representative in <br /> ' monitoring, reviewing and reporting Project status and progress shall relieve the Contractor of <br /> responsibility for planning and managing construction Work in conformance with the <br /> construction schedule. <br /> 5.2.4. Delays <br /> 5.2.4.1 General <br /> ' In the event of a Delay, the Contractor shall take immediate steps to minimize the Delay or <br /> avoid further Delay. The Contractor agrees it shall not make any Contract Claim or request for <br /> adjustment of Contract Time or Contract Sum based upon Delays for which it did not timely <br /> provide Notice to the Owner. <br /> 5.2.4.2 Bonuses <br /> If the Contract Documents provide the Contractor with a bonus or other incentive for early <br /> ' completion of a milestone or other completion point, Contractor assumes the risk of Delays <br /> caused wholly or partially by third parties. Owner shall not pay any bonus that Contractor would <br /> have achieved but for any and all Delays caused in whole or in part by a third party. By way of <br /> example only, the Contractor bears the risk of utility companies' failure to locate underground <br /> ' utilities accurately and the Contractor bears the risk of timely asking for the marking of the <br /> location of underground utilities. <br /> ' 00 7200- 18 GENERAL CONDITIONS <br />