Project: N. Broadway Transit Improvement Project <br /> Change Order No. 1 <br /> Change Order Effective Date: March 15,2019 <br /> Exhibit A—Description of Changed Work: <br /> Change Order No. 1 Modifies 1 bid item and adds 1 new item to the contract as stated below: <br /> Revised Existing Bid Item <br /> Bid Item 22-Cement Concrete Driveway Ramp Type 1. Modify bid item 22 entitled"Cement <br /> Concrete Driveway Type 1",to decrease the contract value at unit price of$116.00 per SY,by <br /> removing 70 SY,resulting in an$8,120.00 decrease to the contact. <br /> Added Bid Items <br /> New Item 118–Cement Concrete Paving. Add new item 118 entitled,"Cement Concrete Paving"at <br /> the agreed to unit price of$202.29 per SY, by adding 83 SY, resulting in an$16,790.07 increase to the <br /> Contract price. <br /> Cost Summary <br /> The net result of the modification of the existing bid item and addition of the new item increases the <br /> contract value by$8,670.07 <br /> Exhibit B-- Justification: <br /> Bid Item 22-Cement Concrete Driveway Ramp Type 1. The installed quantity of"Cement <br /> Concrete Driveway Type 1"under-ran the estimated quantity <br /> New Item; 118 Cement Concrete Pavement. "Cement Concrete Pavement" is added work required <br /> to replace existing roadway in kind as required to complete under-ground utility work. <br /> Exhibit C—Additional Contract Time: <br /> There are 3 additional working days added for this change order. <br /> Page 3 of 3 <br />