thyssenkrupp <br /> Subcontract Change Order Request Date: 07/12/2019 <br /> PROJECT NUMBER: 47179 <br /> CONTRACT DATE: 12/5/2017 <br /> CHANGE ORDER NUMBER: 4 <br /> PROJECT NAME: GRAND AVENUE PARK BRIDGE <br /> PROJECT ADDRESS: 1720 GRAND AVE <br /> EVERETT,WA, 98201 <br /> CONTRACTOR NAME: Interwest Construction Inc <br /> CONTRACTOR ADDRESS: 609 North Hill Blvd <br /> Burlington,WA, 98233 <br /> SUBCONTRACTOR NAME: thyssenkrupp ELEVATOR CORPORATION <br /> SUBCONTRACTOR ADDRESS: 12530 135th Ave <br /> Kirkland, WA, 98034 <br /> This request for a formal Change Order is made for the above-referenced Contractor and specifically intends to modify and amend the <br /> work, price and/or terms set forth in above-referenced Subcontract as follows: <br /> Material Changes: Replace two masonry entrance frames with two new drywall entrances. Labor and material costs in the following breakdown. <br /> Interwest Construction Inc agrees to issue a formal change order to thyssenkrupp Elevator for the described work befo re any associated <br /> material will be ordered. <br /> Grand Ave Bridge-Drywall Entrance Frames $ <br /> Material $ 2,732.80 <br /> Labor-32 HRS $ 10,464.00 <br /> Subtotal $ 13,196.80 <br /> 15%OH&P r$ 1,979.52 <br /> Total $ 15,176.32 <br /> Total Amount of this Change Order to be added to the contract price: $15,176.32 <br /> In the event of any conflict between the work, price and/or terms and conditions of the above-referenced Subcontract or prior change <br /> orders thereto and this Change Order, this Change Order shall be final. Please sign two (2) copies of this Change Order and return <br /> two (2) copies to thyssenkrupp Elevator. A fully executed copy of this Change Order will be returned to you for your files. <br /> Signed Acceptance: <br /> By signing this Change Order where indicated below, the Contractor's signatory hereby acknowledges(a)that the Contractor agrees to <br /> all of the terms and conditions contained herein, (b) that the signatory has the authorization necessary to bind the Contractor to <br /> agreements of this nature, and (c) that this form is valid and binding notwithstanding any conflicts with procedures and/or forms <br /> required by the original Subcontract referenced above which are deemed to have been waived. <br /> This change order/notice scope of work requires the anticipated or current project schedule, and associated time frames, to be <br /> adjusted commensurate with the time necessary for the engineering, material procurement and additional labor. thyssenkrupp <br /> Elevator will provide a revised project schedule on expedited schedule change order/notice scope of work to the purchaser upon <br /> request. <br /> Subcontractor: Contractor: <br /> thyssenkrupp Elevator Corporation Interwest Construction Inc <br /> By: Geoff Gilchrest Date: By: lzaak Fox Date: <br /> Title : Project Manager Title: Project Manager <br />