I <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> the Contractor, will set the Substantial Completion Date. If, after this inspection the <br /> Engineer does not consider the Work substantially complete and ready for its intended <br /> ' use, the Engineer will, by written notice, so notify the Contractor giving the reasons <br /> therefore. <br /> Upon receipt of written notice concurring in or denying substantial completion, whichever <br /> is applicable, the Contractor shall pursue vigorously, diligently and without unauthorized <br /> interruption, the Work necessary to reach Substantial and Physical Completion. The <br /> Contractor shall provide the Engineer with a revised schedule indicating when the <br /> Contractor expects to reach substantial and physical completion of the Work. <br /> The above process shall be repeated until the Engineer establishes the Substantial <br /> Completion Date and the Contractor considers the Work physically complete and ready <br /> for final inspection. <br /> 1-05.11(2) Final Inspection and Physical Completion Date <br /> When the Contractor considers the Work physically complete and ready for final <br /> inspection, the Contractor, by written Notice, shall request the Engineer to schedule a <br /> final inspection. The Engineer will set a date for final inspection. The Engineer and the <br /> Contractor will then make a final inspection and the Engineer will notify the Contractor <br /> in writing of all particulars in which the final inspection reveals the Work incomplete or <br /> unacceptable. The Contractor shall immediately take such corrective measures as are <br /> necessary to remedy the listed deficiencies. Corrective work shall be pursued vigorously, <br /> diligently, and without interruption until physical completion of the listed deficiencies. This <br /> process will continue until the Engineer is satisfied the listed deficiencies have been <br /> corrected. <br /> If action to correct the listed deficiencies is not initiated within seven days after receipt <br /> of the written notice listing the deficiencies, the Engineer may, upon written notice to the <br /> Contractor, take whatever steps are necessary to correct those deficiencies pursuant to <br /> 1-05.7 REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK. <br /> ' The Contractor will not be allowed an extension of Contract Time because of a Delay in <br /> the performance of the Work attributable to the exercise of the Engineer's right under <br /> the authority of the Contract. <br /> Upon correction of all deficiencies, the Engineer will notify the Contractor and the City, <br /> in writing, of the date upon which the Work was considered physically complete. That <br /> date shall constitute the Physical Completion Date of the Contract, but shall not imply <br /> 1 acceptance of the Work or that all the obligations of the Contractor under the Contract <br /> have been fulfilled. <br /> 1-05.11(3) Operational Testing <br /> It is the intent of the City to have at the Physical Completion Date a complete and <br /> operable system. Therefore when the Work involves the installation of machinery or <br /> other mechanical equipment; street lighting, electrical distribution or signal systems; <br /> irrigation systems; buildings; or other similar work it may be desirable for the Engineer <br /> to have the Contractor operate and test the Work for a period of time after final inspection <br /> but prior to the Physical Completion Date. Whenever items of Work are listed in the <br /> Contract Documents for operational testing they shall be fully tested under operating <br /> conditions for the time period specified to ensure their acceptability prior to the Physical <br /> Completion Date. During and following the test period, the Contractor shall correct any <br /> ' items of workmanship, materials, or Equipment that prove faulty, or that are not in first <br /> class operating condition. Equipment, electrical controls, meters, or other devices and <br /> Equipment to be tested during this period shall be tested under the observation of the <br /> Engineer, so that the Engineer may determine their suitability for the purpose for which <br /> Watermain Replacement"U" Division 1 —GENERAL REQUIREMENTS October 1, 2019 <br /> 1 WO No—UP3698 SP—67 <br />