Table 2: Amendment 2 Project Schedule per Subtask <br /> Task i . <br /> Subtask 8.1 Amendment 2 Project Management (For Design and Construction Phases) <br /> Anticipated NTP 3/19/2020 <br /> Project Management throughout life of project 3/19/2020 9/4/2020 <br /> Develop Internal Project Execution Plan 3/20/2020 3/26/2020 <br /> Internal KO Call 3/20/2020 <br /> Update Field Safety Plan (FSP) 3/20/2020 3/26/2020 <br /> Subtask 8.2 SEI to SRI Intertie Final Design <br /> Develop 100% bid-set documents and draft cost estimate 3/23/2020 4/2/2020 <br /> Internal QAQC (technical and constructability) review of 100% bid set documents and draft cost estimate 4/3/2020 4/13/2020 <br /> Implement internal review comments 4/14/2020 4/22/2020 <br /> Submit 100% bid set documents and draft cost estimates 4/23/2020 <br /> City conducts review and provides review comments on deliverables 4/24/2020 5/5/2020 <br /> Implement City review comments 5/6/2020 5/19/2020 <br /> Submit final bid-set documents, final cost estimates and responses to City review comments 5/20/2020 <br /> Subtask 8.3 SRO8 Pipeline - New Manhole Structure-Final Design <br /> Develop 100% bid-set documents and draft cost estimate 3/23/2020 4/2/2020 <br /> Internal QAQC (technical and constructability) review of 100% bid set documents and draft cost estimate 4/3/2020 4/13/2020 <br /> Implement internal review comments 4/14/2020 4/22/2020 <br /> Submit 100% bid set documents and draft cost estimates 4/23/2020 <br /> City conducts review and provides review comments on deliverables 4/24/2020 5/5/2020 <br /> Implement City review comments 5/6/2020 5/19/2020 <br /> Submit final bid-set documents, final cost estimates and responses to City review comments 5/20/2020 <br /> Subtask 8.4 SRO8 Leaking Hatch -Final Design <br /> Develop 100% bid-set documents and draft cost estimate 3/23/2020 4/2/2020 <br /> Internal QAQC (technical and constructability) review of 100% bid set documents and draft cost estimate 4/3/2020 4/13/2020 <br /> Implement internal review comments 4/14/2020 4/22/2020 <br /> Submit 100% bid set documents and draft cost estimates 4/23/2020 <br /> City conducts review and provides review comments on deliverables 4/24/2020 5/5/2020 <br /> Implement City review comments 5/6/2020 5/19/2020 <br /> Submit final bid-set documents, final cost estimates and responses to City review comments 5/20/2020 <br /> Subtask 8.5 Lift Station#1 Valve Vault-PreDesign <br /> Develop 60% design plans and specifications and draft cost estimate 3/23/2020 3/30/2020 <br /> Internal QAQC review of 60% plans and specifications and draft cost estimate 3/31/2020 4/14/2020 <br /> Implement internal review comments 4/15/2020 4/29/2020 <br /> Submit 60% design plans and specifications and draft cost estimate to City 4/30/2020 <br /> Page 10 <br />