IMCO General Construction Inc 4/15/2020 Change Order 4
>
Contracts
>
Capital Contract
>
IMCO General Construction Inc 4/15/2020 Change Order 4
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
4/27/2020 12:21:56 PM
Creation date
4/27/2020 12:21:49 PM
Metadata
Fields
Template:
Contracts
Contractor's Name
IMCO General Construction Inc
Approval Date
4/15/2020
Department
Public Works
Department Project Manager
Zachary Brown
Subject / Project Title
WPCF FEN Chlorination Building Upgrade
Public Works WO Number
UP3614
Amendment/Change Order
Change Order
Amendment/Change Order Number
4
Tracking Number
0001476
Total Compensation
$26,734.56
Contract Type
Capital Contract
Retention Period
10 Years Then Transfer to State Archivist
Document Relationships
IMCO General Construction Inc 11/13/2018
(Amendment)
Path:
\Documents\City Clerk\Contracts\Capital Contract
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
4
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
Project: WPCF Chlorination Building Upgrade <br /> Change Order No. 04 <br /> Change Order Effective Date: March 31,2020 <br /> CONTRACTOR <br /> Digdayyllgned by CJ Handforth <br /> CJ Handforth owD� <br /> £chandferth@imcoconstruc6on com, <br /> DN dforth April 1 , 2020 <br /> Date_2020 02D 04 07 10 32 23-07'00' <br /> By Date: <br /> Officer <br /> Exhibit A—Description of Changed Work <br /> Change Order#4 adds one (1) new Item#13,titled—Combined Work Change Directives 37, 38&41 <br /> to the Contract in the agreed to lump sum price of$26,734.56. <br /> Individual work change directives are defined & justified as follows: <br /> Work Change Directive 037: Revise Sodium Hypochlorite Metering Pump Piping. <br /> Increases the Contract Amount by$10,000.86. <br /> Work Change Directive 038:Temporary Repairs at Outfall Manhole. <br /> Increases the Contract Amount by$11,626.70. <br /> Work Change Directive 041: Carrier Water Pumps Piping Revisions. <br /> Increases the Contract Amount by$5,107.00. <br /> JUSTIFICATION: <br /> Work Change Directive 037:The per plan piping layout for the hypochlorite and ammonia metering <br /> pumps did not allow the pressure measurement instrumentation to measure the discharge pressure <br /> of the metering pumps. Measurement of the pump's discharge pressure is required for the proper <br /> control of the metering pumps. WCD 037 revised the piping so the pump's discharge pressure could <br /> be measured. <br /> The per plan piping layout for the hypochlorite metering pumps did not allow one of the two pumps <br /> to be isolated for maintenance, while the other pump remained online, providing disinfection. <br /> Extensive modifications to the inlet and discharge piping were required. <br /> The per plan piping layout for the hypochlorite and ammonia metering pumps did not provide <br /> support for the pressure and flow measurement instrumentation. The instrumentation was held in <br /> place by the process piping only. Without proper support of the instrumentation, the process piping <br /> will develop leaks jeopardizing operations and maintenance personnel, as well as the disinfection <br /> process. WCD 037 added supports for the pressure and flow measurement instrumentation. <br /> Page 3 of 4 <br />