Project: WPCF Chlorination Building Upgrade <br /> Change Order No. 02 <br /> Change Order Effective Date: January 24, 2020 <br /> CONTRACTOR <br /> By Date: ( `7 l zv Z <br /> Officer <br /> Exhibit A—Description of Changed Work <br /> 1. Change Order#2 is a time only Change Order. This Change Order formally adds the calendar <br /> days previously agreed to in the individual Work Change Directives. <br /> 2. Add the following calendar days to WO 3614. <br /> WCD-001 Added Bank Armoring: Increase Contract Time by 2-Days. <br /> WCD-002 Move Box Culvert: Increase Contract Time by 2-Days. <br /> WCD-003 Revise Fall Protection: Increase Contract Time by 5-days. <br /> WCD-005 Metering Pump Power Revision: Increase Contract Time by 1-Day. <br /> WCD-006 Generator Conduit Revision: Increase Contract Time by 1-Day. <br /> WCD-007 Roof Joist Revisions: Increase Contract Time by 6-Days. <br /> WCD-019.01 Additional Fall Restraint System: Increase Contract Time by 1-Day. <br /> WCD-020 Revise CMU Reinforcing Steel: Increase Contract Time by 5-Days. <br /> WCD-023 Added Containment Trench Coating: Increase Contract Time by 3-Days. <br /> WCD-030 Provide and Install Instrumentation Cable: Increase Contract Time by 1-Day. <br /> WCD-031 Outfall Dewatering Pipe Extension: Increase Contract Time by 1-Day. <br /> WCD-033 Relocate Unit Heater 510: Increase Contract Time by 1-Day. <br /> WCD-034 Revise IGP Pressure Indicating Transmitters: Increase Contract Time by 1-Day. <br /> WCD-035 Additional Valve Tags: Increase Contract Time by 1-Day. <br /> WCD-036 Revise Pipe Labels: Increase Contract Time by 1-Day. <br /> WCD-037 Revise Metering Pump Piping: Increase Contract Time by 1-Day. <br /> WCD-038 Temporary Repairs—Outfall Manhole: Increase Contract Time by 2-Days. <br /> WCD-040 Salvage Existing Communications Cable: Increase Contract Time by 1-Day. <br /> Total: 36-Days <br /> JUSTIFICATION: <br /> Please see the respective Work Change Directives. <br /> Page 3 of 3 <br />