b) Design-Builder failed to give the written notice as required by <br /> Section 4.2 and/or comply with Article 9. <br /> 4.2.2.3 If Design-Builder knows or should have known of a Differing Site Condition during <br /> the design phase of the Project, but fails to mitigate by taking the Differing Site Condition <br /> into account in its design,the adjustment to Contract Time or Contract Price will be limited <br /> to the adjustment, if any, that Design-Builder would have been entitled to if Design-Builder <br /> had not so failed to mitigate. <br /> 4.2.2.4 If Design-Builder complies with the provisions of Article 9 and this Section 4.2 and <br /> Owner and Design-Builder are unable to agree on entitlement to or on the amount or extent, <br /> if any, of any adjustment in the Contract Price or Contract Time, or both, a Claim may be <br /> made by Design-Builder as provided in Article 10. <br /> Article 5 <br /> Non-Discrimination <br /> 5.1 Design-Builder shall not discriminate on the grounds of race, color, sex or national origin in the <br /> selection and retention of Subcontractors, including procurement of materials and leases of <br /> equipment. Design-Builder shall not participate either directly or indirectly in such discrimination, <br /> including discrimination in employment practices. In the event of Design-Builder's noncompliance <br /> with the nondiscrimination provisions of the Contract Documents, Owner shall impose such <br /> sanctions as it, or the Owner's funding agencies, may determine to be appropriate, including, but <br /> not limited to: (a)withholding of payments to Design-Builder until Design-Builder complies, and (b) <br /> termination or suspension of the Contract, in whole or in part. <br /> 5.2 Design-Builder shall actively and in good faith solicit the employment of minority group members <br /> and bids for the supply of goods or subcontracting of services from qualified minority businesses. <br /> Design-Builder shall consider granting contracts to possible minority suppliers and Subcontractors <br /> on the basis of substantially equal proposals in the light most favorable to the minority businesses. <br /> As requested by Owner, Design-Builder shall furnish evidence of its compliance with these <br /> requirements. As used in this section,the term "minority business"means a business at least 51% <br /> of which is owned by minority group members. Minority group members include, but are not limited <br /> to, African-Americans, Women, Native Americans, Asian/Pacific Islander-Americans, and <br /> Hispanic-Americans. <br /> Article 6 <br /> Payment <br /> 6.1 Schedule of Values <br /> 6.1.1 The Design-Builder shall submit a Schedule of Values at least 15 days prior to submitting <br /> their first Application for Payment. The Schedule of Values shall reasonably allocate the Contract <br /> Sum among the various portions of the Work; be complete; be organized to include detailed <br /> breakdown of each major unit of the Work; be organized to correspond to Design-Builder's <br /> schedule; break down the Contract Sum showing the value assigned to each part of the Work; be <br /> so organized as to facilitate assessment of work and payment of Subcontractors;and be balanced. <br /> To the greatest extent possible, the breakdown shall use the same tasks or units as the Design- <br /> Builder's CPM schedule. Design-Builder shall provide documentation substantiating the cost <br /> allocation if asked by the Owner. Upon acceptance of the Schedule of Values by the Owner, it shall <br /> be used as a basis for all requests for payment. <br /> 6.1.2 The Owner will timely review and approve the Schedule of Values so as not to delay the <br /> East Clearwell Project General Conditions of Contract Page 13 <br />