• 1 <br /> Exhibit F <br /> BNSF Bridge Requirements <br /> BRIDGE DESIGN,PLANS&SPECIFICATIONS: <br /> Except for the design of temporary falsework and shoring,BNSF review of the Structure plans will be limited to the <br /> vertical and horizontal clearances, sight distance for existing train signals, foundation dimensions and drainage <br /> characteristics as they relate to existing and future tracks.BNSF will not review structural•- 1l calculations for the <br /> permanent Structure unless a member or members are influenced by railroad live loads <br /> Temporary falsework and shoring plans and calculations must be 4f-wed an'i rprov-.1 ,,. Be F prior to <br /> beginning construction. The Agency shall perfonn an independent revie he d- c if.tions`Ml7l temporary <br /> falsework and shoring prior to submitting them to BNSF for approval.Tem,o _i co. on cle. •)ir-s must be <br /> no less than 15 feet measured horizontally from the centerline of the neares'< ,�an. ).f i i ee-'it4 r`s measured <br /> vertically from the top of rail of the most elevated track to the bottom • est to rihti)_.. i - 201'.1 ember. State <br /> regulatory agencies may have more restrictive requirements for to Sw r ,d c :.10u_ es. <br /> For the permanent Structure,the Agency will submit plans shy N)s a e least ho k&tal di ce from the centerline <br /> of existing and future tracks to the face of the nearest member . E 4,proposed WI ture. The location of the least <br /> horizontal distance must be accurately described suc. .or_..BNS 'ro•.determine where it will occur in. both the <br /> horizontal and vertical plane. If the permanent me1i1 ,?''thin "S fe- !_t? ?nearest track (or future track), <br /> collision walls shall be incorporated into the p �.�'anent cry_ ture it4iff.1 according to American Railway <br /> Engineering and Maintenance Association M. 111��_i'�-commen=l Sri'-actic, apter 8-Article 2.1.5. <br /> For the permanent Structure,the Agency .i bmit p:i't,',+owing th "east verti.a clearance from top of the most <br /> elevated rail of existing and future tracks o ii owest poioh (4 the proposed Structure. A profile of the existing top <br /> of rail elevation shall be plotted on the bri.: Di ans.The p u tit;.,shall extend for 500 feet in each direction of the <br /> proposed overpass and a separa 1 a_il- shall jetted for e• h track. If the existing top of`rail profile(s)is not <br /> uniform such that a sag exist AIL h e c 14 of 1 .used Structure,the permanent Structure vertical clearance <br /> shall be increased sufficient,i.. acco ''a e a ra° : the track profile to remove the sag. Prior to beginning <br /> construction •r- '--'ermanen� i.± c V i e'o. •_rail elevations should be checked and verified that they have not <br /> changed .'.i 1 he-.xsi;rned ele :do ' -d • c l•"-;'design of the bridge. <br /> i <br /> Prior t.+ suing any in t'o„to b ction of the Structure,the Agency should conduct a pre-bid meeting <br /> where ID Rective Co • 'o l!•ve 4'- 'p•ortunity to communicate with BNSF personnel regarding site specific <br /> train speed§ ji o rty, an. :e o eral safety requirements for men and equipment working near live tracks. Any <br /> invitation to"o fa .d specifica:'% for the Structure must be submitted to BNSF for review and approval prior to <br /> letting of bids for the Project. / <br /> / <br /> BRIDGE CONST1k a!: <br /> After awarding the bid, but prior to the Contractor entering BNSF's right-of—way or property,the Agency should <br /> conduct a pre-construction meeting with BNSF personnel in attendance to reiterate the safety requirements of <br /> construction activity adjacent to live tracks. <br /> During construction, BNSF may require an independent engineering inspector to be present during certain critical <br /> activities of the Project, including but not limited to: driving foundation piles, erecting falseworlc, construction of <br /> shoring and retaining walls, placing concrete, placing soil backfill and compaction processes. The Agency shall <br /> reimburse BNSF for all costs of supplemental inspection services. <br /> Within 90 days of the conclusion of the Project and final acceptance by BNSF,the Agency will provide BNSF with <br /> a complete electronic set of the bridge plans labeled"As Built'.Those plans will reflect any and all deviations from <br /> Form 0105 Rev. 06/01/05 <br /> 47 <br />