2.1.6 Element 6: Protect Slopes <br /> All runoff will be directed away from proposed slopes onsite and these slopes will be temporarily <br /> or permanently seeded, or covered during construction with plastic or erosion control netting. <br /> There are no steep slopes within the limits of work. Stockpile slopes will be covered with plastic <br /> while unused. <br /> Will steep slopes be present at the site during construction? <br /> ❑ Yes® No <br /> List and describe C120—Temporary and Permanent Seeding, BMPs: C122— Nets and <br /> Blankets, C123— Plastic Covering <br /> Installation Schedules: During earthmoving activity and maintained throughout construction. <br /> Inspection and Maintenance plan: Wet Season: Weekly and after heavy rainfall, Dry Season: <br /> Monthly and after rainfall. See Appendix B <br /> Responsible Staff: TBD <br /> Page 111 <br />