Stormwater Pollution Prevention Plan <br /> 4.0 Construction Phasing and BMP <br /> Implementation <br /> The BMP implementation schedule will be driven by the construction schedule. The following <br /> provides a sequential list of the proposed construction schedule milestones and the <br /> corresponding BMP implementation schedule. The list contains key milestones such as wet <br /> season construction. <br /> The BMP implementation schedule listed below is keyed to proposed phases of the construction <br /> project, and reflects differences in BMP installations and inspections that relate to wet season <br /> construction. The project site is located west of the Cascade Mountain Crest. As such, the dry <br /> season is considered to be from May 1 to September 30 and the wet season is considered to be <br /> from October 1 to April 30. <br /> • Estimate of Construction Start Date Oct 2017 <br /> • Estimate of Construction End Date September 2018 <br /> • Mobilize equipment on site: Oct 2017 <br /> • Mobilize and store all ESC and <br /> soil stabilization products: Oct 2017 <br /> • Install ESC measures: Oct 2017 <br /> • Install stabilized construction entrance: Oct 2017 <br /> • Begin clearing and grubbing: Oct 2017 <br /> 17 <br />