CITY OF EVERETT SPECIAL PROVISIONS <br /> 1-05.11 Final Inspections and Operational Testing <br /> (******) <br /> 1-05.11(1) Substantial Completion Date <br /> When the Contractor considers the Work to be substantially complete, the Contractor <br /> shall so notify the Engineer and request the Engineer establish the Substantial <br /> Completion Date. The Contractor's request shall list the specific items of Work that <br /> remain to be completed in order to reach physical completion. The Engineer will <br /> schedule an inspection of the Work with the Contractor to determine the status of <br /> completion. The Engineer may also establish the Substantial Completion Date <br /> unilaterally. <br /> If, after this inspection, the Engineer concurs with the Contractor that the Work is <br /> substantially complete and ready for its intended use, the Engineer, by written notice to <br /> the Contractor, will set the Substantial Completion Date. If, after this inspection the <br /> Engineer does not consider the Work substantially complete and ready for its intended <br /> use, the Engineer will, by written notice, so notify the Contractor giving the reasons <br /> therefore. <br /> Upon receipt of written notice concurring in or denying substantial completion, whichever <br /> is applicable, the Contractor shall pursue vigorously, diligently and without unauthorized <br /> interruption, the Work necessary to reach Substantial and Physical Completion. The <br /> Contractor shall provide the Engineer with a revised schedule indicating when the <br /> Contractor expects to reach substantial and physical completion of the Work. <br /> The above process shall be repeated until the Engineer establishes the Substantial <br /> Completion Date and the Contractor considers the Work physically complete and ready <br /> for final inspection. <br /> 1-05.11(2) Final Inspection and Physical Completion Date <br /> When the Contractor considers the Work physically complete and ready for final <br /> inspection, the Contractor, by written Notice, shall request the Engineer to schedule a <br /> final inspection. The Engineer will set a date for final inspection. The Engineer and the <br /> Contractor will then make a final inspection and the Engineer will notify the Contractor <br /> in writing of all particulars in which the final inspection reveals the Work incomplete or <br /> unacceptable. The Contractor shall immediately take such corrective measures as are <br /> necessary to remedy the listed deficiencies. Corrective work shall be pursued vigorously, <br /> diligently, and without interruption until physical completion of the listed deficiencies. This <br /> process will continue until the Engineer is satisfied the listed deficiencies have been <br /> corrected. <br /> If action to correct the listed deficiencies is not initiated within seven days after receipt <br /> of the written notice listing the deficiencies, the Engineer may, upon written notice to the <br /> Contractor, take whatever steps are necessary to correct those deficiencies pursuant to <br /> 1-05.7 REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK. <br /> The Contractor will not be allowed an extension of Contract Time because of a Delay in <br /> the performance of the Work attributable to the exercise of the Engineer's right under <br /> the authority of the Contract. <br /> Upon correction of all deficiencies, the Engineer will notify the Contractor and the City, <br /> in writing, of the date upon which the Work was considered physically complete. That <br /> date shall constitute the Physical Completion Date of the Contract, but shall not imply <br /> acceptance of the Work or that all the obligations of the Contractor under the Contract <br /> have been fulfilled. <br /> Jackson Park Area Stormwater Separation <br /> WO No—UP3703 Division 1 —GENERAL REQUIREMENTS September 2020 <br /> SP-66 <br />