Silver Lake Plaza <br />Minimum Requirement # 2: SWPPP Narrative <br />Element #1: Mark Clearing Limits <br />Clearing limits have been shown on the SWPPP Plan. <br />Element #2: Establish Construction Entrance <br />A temporary construction entrance at the southwest corner of the site connecting to 19th <br />Avenue SE has been shown on the SWPPP plan. All vehicles shall be free of debris prior to <br />leaving the site. <br />Element # 3: Control Flow Rates <br />Flow rates during construction are to be contained through the installation of a temporary <br />silt fencing on the south and west sides of the site. <br />Element # 4: Install Sediment Controls <br />Sediment controls mainly consist of installation of a temporary silt fencing on the south <br />and west sides of the site. <br />Element # 5: Stabilize Soils <br />All soils disturbed during site grading will be stabilized by use of the most appropriate <br />BMP method available. These consist of short-term and long-term solutions. Short-term <br />methods consist of compaction of the soils by vibratory roller or bulldozer. Long-term <br />methods consist of straw covering over the soils (this is in the case of the project becoming <br />dormant for greater than 1 month). At this time no wintertime grading or construction <br />activities will occur. During construction periods longer than 1 working week (7 days) <br />where the soils are exposed and un-worked will use the proscribed methods in the Storm <br />Water Management Manual for Western Washington to reduce sedimentation transported <br />offsite. If winter grading is conducted, all exposed soils shall be covered within 2 days. <br />Element # 6: Protect Slopes <br />No steep slopes exist on -site; steep slope protection is not required. <br />Element # 7: Protect Drain Inlets <br />All catch basins within 500 feet downstream of the site will be protected with catch basin <br />sediment inserts. <br />Element # 8: Stabilize Channels and Outlets <br />Channels and drainage outlets are not needed around the proposed development area on <br />site. No stabilization is necessary. Existing channels or drainage outlets located within 500- <br />feet of the property of the property should be routinely inspected for debris that may dam <br />and/or aid erosion. <br />Element # 9: Control Pollutants <br />All pollutants from construction vehicles will be contained and disposed of in the approved <br />manner consistent with state environmental policies. Any vehicle maintenance will be <br />performed by authorized mechanics using drip pans and waste containment vessels. All <br />pollutants will be disposed offsite at approved facilities. <br />WESTERN ENGINEERS, INC. 12 PROJECT: 15-1415-A <br />