i <br /> 2021-01-26 <br /> Addendum No.2 <br /> ANSWER: Two separate bonds are required. The landscape maintenance bond covers the landscape <br /> and temporary irrigation maintenance work to be performed after project completion. Payment to the <br /> Contractor for post-construction maintenance will be made with the final payment to the Contractor. The <br /> bidder's attention is also called to the technical specifications, Section 32 92 23, Hydroseeding and Sod, <br /> Part 1,paragraph 1.4, A, 4, a (as amended by this change order (Revision 6 above). <br /> 1 QUESTION 5: For this project, is the installation of the quick coupling valve to be included in the landscaping <br /> portion of the bid? <br /> ANSWER: Yes <br /> 1 <br /> QUESTION 6: I was hoping for clarification on the amount of working or calendar days OR completion date for <br /> project PW#: 2020-064-RI. <br /> ANSWER:Please see Addendum No. 1 <br /> The bidder's attention is directed to the Bid Form, section 00 41 13, section 12, wherein the <br /> Bidder's acknowledgement of receipt of this Addendum is required. A signed copy of this <br /> Addendum is also required to be submitted with each bid. <br /> By: <br /> Bidder firm name <br /> By: <br /> Signature, title and date <br /> End of Addendum #2 <br /> Mark Harrison <br /> Parks Planning & Capital Development Manager <br /> 802 E. Mukilteo Blvd. Everett, WA 98203 <br /> mharrison@everettwa.gov <br /> 0: 425-257-8378 C:425.244.8182 <br /> 1 <br /> I <br /> I <br /> Emma Yule Park—Addendum No 2 <br /> I <br />