Laserfiche WebLink
CITY OF EVERETT SPECIAL PROVISIONS <br /> ' 1. Documented, incurred cost of nonproductive field supervision or labor <br /> extended because of the delay; <br /> 2. Documented, incurred cost of home office supervision to attend jobsite <br /> meetings; <br /> 3. Documented, incurred cost of temporary facilities or equipment rental <br /> ' extended because of the Delay; <br /> 4. Documented, incurred cost of insurance extended because of the Delay; <br /> 5. General and administrative overhead in an amount to be agreed upon, but <br /> ' not to exceed three percent of original Contract Sum divided by the Contract <br /> Time for each day of the Delay. <br /> City shall not owe Contractor compensation for Extended Overhead or other delay costs <br /> to the extent Contractor or anyone other than the City contributed to or is concurrently <br /> responsible for the Delay. <br /> 1-09.11A(3)A2 Adjustment of Contract Time <br /> If the Contractor is entitled to an adjustment of Contract Time because of a Delay solely <br /> caused by the City that does not relate to Extra Work, Contractor shall be entitled to an <br /> adjustment of Contract Time to the extent the Delay increases the duration of the Project, <br /> ' as measured by the critical path and as demonstrated pursuant to the requirements of <br /> 1-08.8 EXTENSIONS OF TIME. <br /> 1-09.11A(3)B Contractor Caused Delay <br /> ' If the Contractor is solely responsible for any Delay to any interim milestone, Substantial <br /> Completion, Physical Completion, or the Completion Date, the City shall be entitled to <br /> liquidated or other damages as provided elsewhere in the Contract Documents. The <br /> ' Contractor accepts the risk of any Delays caused by strikes, work slowdowns, job actions <br /> and labor unrest of any kind. Contractor shall not be entitled to any increase in Contract <br /> Sum or Contract Time due to a Delay it caused. <br /> 1-09.11A(3)C Delays Concurrently Caused by Contractor and Owner <br /> If the City and the Contractor cause a Delay concurrently, neither the City nor the Contractor <br /> shall be liable to the other except as provided herein. <br /> 1-09.11A(3)C1 Adjustment of Contract Sum <br /> The Contractor shall not be entitled to any adjustment in Contract Sum for Delays <br /> concurrently caused by the City and the Contractor. <br /> 1-09.11A(3)C2 Adjustment of Contract Time <br /> The Contractor shall be entitled to an extension of Contract Time for the City caused <br /> portion of any Delay concurrently caused by the City and Contractor to the extent the <br /> City caused the Delay to extend longer than if the Contractor had solely caused the <br /> Delay. <br /> I <br /> I <br /> SEI to SRI Intertie,SRO8 Rehab Division 1 —GENERAL REQUIREMENTS WO No.—UP3714 <br /> SP—115 <br />