I <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> I2. Because of the Delay described in subsection (1), the Contractor was forced <br /> to suspend or significantly interrupt its performance so that it was on standby <br /> I or idled, and the City required the Contractor to be ready to resume <br /> performance on short notice. Extended time of performance of Work, such <br /> as extensions caused by changes, inefficiencies, or extra Work, does not <br /> I constitute suspension or significant interruption of performance. <br /> 3. The Contractor could not and did not use resources, including, but not limited <br /> to, labor, equipment, materials and tools, standing by or idled on this or other <br /> I project for any Work during the period of Delay; <br /> 4. The Contractor's Overhead costs did not materially vary from its usual <br /> seasonal Overhead costs during the period of Delay; and <br /> I 5. The Delay did not cause over absorbed Overhead in the period the delayed <br /> Work was completed. <br /> 1-09.11 A(4)A1 a Resources <br /> I To demonstrate the Contractor could not and did not use resources, including, but <br /> not limited to, labor, equipment, materials and tools from this Project for any other <br /> work on this or any other project during the period of Delay in accordance with <br /> item 3 of 1-09.11A(4)A1 of these Special Provisions, the Contractor shall: <br /> I1. Affirmatively represent and warrant that it did not perform substitute <br /> Work; <br /> 2. Identify the specific resources that were idled; and <br /> I3. Show that those resources did not, and could not, work on other <br /> contracts or projects during the Delay. <br /> 1-09.11A(4)A1b No Material Variations <br /> ITo demonstrate the Contractor's Overhead costs did not materially vary from its <br /> usual seasonal Overhead costs during the period of Delay in accordance with <br /> item 4 of 1-09.11A(4)A1 of these Special Provisions, the Contractor shall; <br /> ' 1. Affirmatively represent and warrant that the completion of the subject <br /> Work was extended and that such extension prevented the performance <br /> of other work during both the period of Delay and the later period of time <br /> I <br /> required to complete the extended Work, <br /> 2. Disclose the details of Contractor generated billings and Contractor <br /> Overhead Costs, as defined in these Special Provisions, throughout the <br /> I actual Project performance. The details of such information should be <br /> no less than specific identification of the sources and amounts of <br /> revenue on no greater than a monthly basis and specific identification of <br /> I the types and amounts of Contractor Overhead Costs on no greater than <br /> a monthly basis for the actual Project duration. <br /> 1-09.11A(4)A1c Over-absorbed Overhead <br /> I To demonstrate that Contractor did not incur Over-absorbed Overhead in the <br /> period following the Delay, in accordance with item 5 of 1-09.11A(4)A1. of these <br /> Special Provisions, the Contractor shall: <br /> 1. Affirmatively represent and warrant that completion of the delayed Work <br /> prevented the performance of other Work; <br /> 2. Identify the critical resource unavailable for other Work due to completion <br /> of the delayed Contract; and <br /> I 3. Showing that unavailability of this critical resource precluded the <br /> performance of other Work. <br /> I SEI to SRI Intertie,SRO8 Rehab Division 1 -GENERAL REQUIREMENTS WO No.-UP3714 <br /> SP-117 <br /> I <br />