' CITY OF EVERETT SPECIAL PROVISIONS <br /> the Contract. This certification shall be submitted to the Engineer on WSDOT form 140-542 within <br /> 20 calendar days after physical completion of the Contract. <br /> ' Supplement 1-08.1 by adding the following: <br /> The Contract Documents shall apply to Subcontractors and suppliers as if each had signed the <br /> Contract with the City. Contractor shall include the provisions of these Contract Documents or a <br /> "flow down" clause in each contract with Subcontractors and suppliers. <br /> The City will not approve a Subcontractor that is also providing services to the City on the same <br /> project. <br /> No Subcontractor or lower tier subcontractor will be permitted to perform Work under the Contract <br /> until the following documents have been completed and submitted to the Engineer: <br /> ' 1. Request to Sublet Work (Form 421-012), and <br /> 2. Contractor and Subcontractor or Lower Tier Subcontractor Certification for Federal-aid <br /> Projects (Form 420-004). <br /> The Contractor's records pertaining to the requirements of this Special Provision shall be open <br /> to inspection or audit by representatives of the City during the life of the Contract and for a period <br /> of not less than three years after the date of acceptance of the Contract. The Contractor shall <br /> retain these records for that period. The Contractor shall also guarantee that these records of all <br /> Subcontractors and lower tier subcontractors shall be available and open to similar inspection or <br /> audit for the same time period. <br /> Contractor shall not sublet to a single Subcontractor more than one-half of the Project. The City <br /> ' may refuse to approve any subcontract for any reason. Subcontractors will be considered agents <br /> of the Contractor and their work shall be subject to the provisions of the Contract. References in <br /> the Contract Documents to actions required of Subcontractors, manufacturers, suppliers, or any <br /> ' person other than the Contractor, the City or the City's Representative shall be interpreted as <br /> requiring that the Contractor shall require such Subcontractor, manufacturer, supplier or person <br /> to perform the specified action. <br /> ' 1-08.3 Progress Schedule <br /> 1-08.3(1) General Requirements <br /> Delete 1-08.3(1) and substitute the following: <br /> 1-08.3(1) General <br /> (******) <br /> Because time is of the essence, diligent and expeditious progress and completion of the Work by <br /> the Contract Completion Date is required of the Contractor. Careful, adequate, accurate and <br /> complete planning and scheduling of the Work by the Contractor, both prior to the start of, and <br /> throughout, construction, is vital to the success of this Project for both the Contractor and the City. <br /> The purposes of the schedules and reports include: <br /> 1. Ensuring adequate planning and execution of the Work by the Contractor. <br /> 2. Assisting the City or its representative in monitoring construction. <br /> 3. Assessing the impact of any actual, potential or proposed change, including, but not <br /> limited to, the financial impact resulting from schedule changes and changes to the <br /> scope of Work. <br /> ' 4. Supporting the basis for construction payments. <br /> 5. Planning by City and tenants. <br /> 6. Avoiding additional or extra costs or expenses to the City. <br /> All schedules will be reviewed by the City and the City's Representative. The City or City's <br /> Representative's review of any schedule shall not transfer the Contractor's responsibilities to the <br /> City. Review shall not constitute approval or acceptance of the Contractor's construction means, <br /> SEI to SRI Intertie,SROB Rehab Division 1 -GENERAL REQUIREMENTS WO No.-UP3714 <br /> SP-89 <br /> I <br />