Retaining Wall Recommendations Page 4 August 21,2019 <br /> Everett,Washington RGI Project No.2016-072 <br /> Table 2 Structural Fill Compaction ASTM D1557 <br /> Minimum Moisture Content <br /> Location Material Type Compaction <br /> Percentage . Range <br /> Wall Foundation On-site granular or approved 95 +2 -2 <br /> imported fill soils: <br /> Retaining Wall Backfill On-site granular or approved 92 +2 -2 <br /> imported fill soils: <br /> General Fill (slope areas) On-site soils or approved <br /> pimported fill soils: 90 +3 -2 <br /> Placement and compaction of structural fill should be observed by RGI.A representative number <br /> of in-place density tests should be performed as the fill is being placed to confirm that the <br /> recommended level of compaction is achieved. <br /> Fill Slope Above Wall <br /> The permanent fill slope above the wall should be graded with a finished inclination no greater <br /> than 3H:1V. Upon completion of construction,the slope face should be trackwalked, compacted <br /> and vegetated, or provided with other physical means to guard against erosion.All fill placed for <br /> slope construction should meet the structural fill requirements as described above. <br /> Final grades at the top of the slopes must promote surface drainage away from the slope crest. <br /> Water must not be allowed to flow in an uncontrolled fashion over the slope face. The curb <br /> proposed on the edge of the parking and drive area should provide adequate surface water <br /> control into the existing storm drainage system. <br /> Additional Services <br /> RGI is available to provide geotechnical engineering and construction monitoring services during <br /> construction.The integrity of the earthwork and construction depends on proper site preparation <br /> and procedures. In addition, engineering decisions may arise in the field in the event that <br /> variations in subsurface conditions become apparent. <br /> Limitations <br /> This letter is the property of RGI, Ms. Isha Daramy, and her designated agents. Within the limits <br /> of the scope and budget, this letter was prepared in accordance with generally accepted <br /> geotechnical engineering practices in the area at the time this letter was issued. This letter is <br /> intended for specific application to the retaining wall at 4841 in Everett,Washington, and for the <br /> exclusive use of Ms. Isha Daramy and her authorized representatives. No other warranty, <br /> expressed or implied, is made.Site safety, excavation support,and dewatering requirements are <br /> the responsibility of others. <br /> The analyses and recommendations presented in this letter are based upon data obtained from <br /> the explorations performed on site and our observations during the previous work on the wall. <br /> Variations in soil conditions can occur, the nature and extent of which may not become evident <br /> until construction. If variations appear evident, RGI should be requested to reevaluate the <br /> recommendations in this letter prior to proceeding with construction. <br /> I al <br /> RILEYGROUP <br />