Work as soon as possible after the date of the Notice to Proceed and shall prosecute <br /> the Work so that the various portions of the Project shall be completed in accordance <br /> with the Contract Time period. Contractor shall perform its work at such times and in <br /> such ways that the Work is not damaged by weather such as wind, rain, or snow. <br /> Contractor shall correct or repair at its sole expense any Work damaged by weather, <br /> irrespective of whether such damage is covered by insurance. No portions of the <br /> Work where acceptable quality will be affected shall be constructed while unfavorable <br /> conditions exist. By bidding on the Project and executing a Contract to perform the <br /> Work, Contractor agrees the contractually required completion dates are feasible, <br /> reasonable, and achievable for the Contract Sum. Contractor represents that it has <br /> considered all factors relevant to its price and achieving the Completion Dates, <br /> including, but not limited to, weather, Site access, labor conditions and the availability <br /> of materials, supplies and Equipment. Compliance with ARTICLE 10. NOTICE TO <br /> OWNER, ARTICLE 12. CONTRACT CLAIMS, and 5.2,B. Construction Schedule are <br /> conditions precedent to a request for, consideration of, and grant of, any extension of <br /> Contract Time. Failure to request a time extension in the manner and in the time <br /> required by this section, and the Specifications referred to herein, constitutes a waiver <br /> by the Contractor of any and all entitlement to an extension of time and any <br /> adjustment of Contract Sum arising out, or related to, such Delay. <br /> B. Construction Schedule <br /> 1. General <br /> a. Contractor shall submit, update and maintain schedules as required by the <br /> Contract Documents. <br /> b. The Contractor shall provide sufficient material, equipment, and labor to meet <br /> the interim milestones, Substantial Completion, Physical Completion and <br /> Completion Dates provided by the Contract Documents. The Owner allocates its <br /> resources to a Contract based on the total time allowed in the Contract. The <br /> Contractor may submit a schedule indicating Completion Date earlier than the <br /> end of Contract Time, but Owner cannot guarantee its resources will be available <br /> to meet such schedule. Owner shall not pay or be liable for any additional <br /> compensation if the Contractor is not able to meet a schedule that indicates a <br /> Completion Date earlier than the end of Contract Time. <br /> c. Failure to schedule Owner furnished or installed materials and Equipment for <br /> installation on or after its planned arrival pursuant to the Owner's contract with <br /> the supplier or failure to Notify the Owner of tasks dependent upon the fact or <br /> date of arrival of such Owner furnished materials and Equipment, constitute a <br /> waiver by Contractor of any Contract Claim arising out of or related to the <br /> timeliness of the furnishing or installation of such material and Equipment. All <br /> schedules must allow for timely incorporation of any other's work under separate <br /> contract with Owner and for timely incorporation of work provided and installed <br /> by Owner. Unless otherwise expressly authorized in writing by the Owner's <br /> Representative, the Contractor must integrate the schedules with the Schedule <br /> Replacement of Reservoir 2 General Conditions <br /> WO# UP3658 00 72 13 - 25 <br />