I <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> Project by the number of days, (as contractually defined) of Contract <br /> performance. The result is the Daily Rate of Allocable Overhead. I <br /> 3. Determining the gross amount of potential additional compensation for Home <br /> Office Overhead due to the project extension. This is accomplished by <br /> multiplying the Daily Rate of Allocable Overhead by the number of days of <br /> project extension caused solely by the City. This results in the Gross Amount <br /> of Additional Home Office Overhead Compensation. <br /> 4. Adjusting the Gross Amount of Additional Home Office Overhead <br /> Compensation for any additional contribution for Overhead received by the <br /> Contractor on any Change Orders that are being presented and resolved <br /> concurrently with the subject calculation for Unabsorbed and/or Extended <br /> Home Office Overhead. The necessary adjustment would be to reduce the <br /> Gross Amount of Additional Home Office Overhead Compensation by any <br /> additional compensation for Overhead included in any direct cost claims <br /> being resolved concurrently with any claim for Extended and/or Unabsorbed <br /> Home Office Overhead. <br /> Contractor shall not receive compensation for cost of use of equity capital. <br /> Supplement 1-09.4 by adding the following: I <br /> 1-09.4(3) COVID-19 Equitable Adjustments <br /> Contractor's Bid includes all costs necessary for the duration of the Work for compliance <br /> with Baseline COVID-19 Requirements. Contractor's Bid takes into account that <br /> Baseline COVID-19 Requirements may create direct and indirect costs, including <br /> inefficiency and Delay. <br /> Contractor shall have no entitlement to an equitable adjustment or other increase to the <br /> Contract Sum for any direct or indirect costs(including without limitation Delay, cumulative <br /> impact, inefficiency or ripple costs) incurred by the Contractor to comply with the Baseline <br /> COVID-19 Requirements or any COVID-19 Requirements applicable to the Work after Bid <br /> opening that are equal to or less stringent than the Baseline COVID-19 Requirements. <br /> If COVID-19 Requirements applicable to the Work at any time after Bid opening are more <br /> stringent than Baseline COVID-19 Requirements, then equitable adjustment, if any, will <br /> be in accordance with Section 1-09.4 EQUITABLE ADJUSTMENT, Section 1-09.4 <br /> DISPUTES AND CLAIMS, Section 1-09.11A(3)D1 CAUSED SOLELY BY THIRD <br /> PARTIES OR FORCE MAJEURE, and any other relevant provision in the Contract <br /> Documents. <br /> If COVID-19 Requirements applicable to the Work at any time after Bid opening are less <br /> stringent than Baseline COVID-19 Requirements, then the City is entitled to a deductive <br /> change order that deducts from the Contract Sum at least 50% of the Contractor's savings <br /> from those less stringent COVID-19 Requirements. Unless otherwise agreed by the City <br /> in writing,the amount of the deductive change order will be agreed upon prior to Contractor <br /> implementing the less stringent COVID-19 Requirements. I <br /> 1-09.5 Deleted or Terminated Work <br /> Delete the first paragraph, beginning with "The Engineer may delete", and the second 1 <br /> paragraph, beginning with "Payment for completed items", and substitute the following: <br /> The City's Representative may delete Work as provided in 1-04.4 CHANGES or may <br /> terminate the Contract in whole or part as provided in 1-08.10(2) TERMINATION FOR <br /> PUBLIC CONVENIENCE. When the Contract is partially terminated for the City's <br /> convenience, the partial termination shall be treated as a deductive Change Order for <br /> payment purposes under this section. <br /> Water Main Replacement"V" Division 1 —GENERAL REQUIREMENTS April,2021 <br /> WO No—UP3730 SP—108 <br />