Construction Sequence <br />1. Contact the city to schedule a pre -construction meeting. <br />2. Field locate and verify all existing services and utilities within project area. See <br />verification note. Field verify horizontal and vertical locations of utilities and <br />utility connections and provide information to project engineer. <br />3. Establish clearing and grading limits per plan. <br />4. Install catchbasin inlet protection to all existing catchbasins located within 500- <br />ft of the project site and other erosion control measures as needed. <br />5. Schedule an erosion control inspection with the city as needed or required by <br />permit. <br />6. Stabilize all exposed soils as needed throughout all activities. <br />7. Perform improvements per plan. <br />8. All tesc measures shall remain in place and maintained during construction of <br />onsite improvements. <br />9. Arrange final inspection with city. <br />10. Remove tesc measures when allowed by the city. <br />Responsible CESCL <br />Name: <br />Phone: <br />Construction Schedule <br />Construction is anticipated to begin as soon as the appropriate permits are acquired. <br />Financial/Ownership Responsibilities <br />Tekin & Associates, LLC <br />2600 N Dallas Parkway, STE 3 <br />Frisco, Texas 75034 <br />