Laserfiche WebLink
CITY OF EVERETT SPECIAL PROVISIONS <br /> Upon written request, the City's Representative shall determine whether the actual conditions <br /> encountered by the Contractor conditions are materially different and, if so, are the cause of <br /> a material increase or decrease in the Contractor's cost of performance of the Work, or extend <br /> the duration of the critical path of the schedule. Upon such determination, the City's <br /> Representative will make an adjustment of Contract Sum or Contract Time, as appropriate. <br /> Extensions of Contract Time will be evaluated in accordance with 1-08.3 PROGRESS <br /> SCHEDULE. <br /> The City's Representative's determination that differing site conditions do not exist and/or the <br /> appropriate adjustment in Contract Sum or Contract Time (if any) shall be final. If there is a <br /> decrease in the cost or time required to perform the Work, failure of the Contractor to notify <br /> the City's Representative of the differing site condition shall not affect the City's right to make <br /> an adjustment in the Contract Sum or Contract Time. Additionally, no Contract Claim or <br /> adjustment of Contract Sum or Contract Time shall be allowed unless the Contractor has <br /> followed the procedures provided for in this Contract, including, but not limited to, furnishing <br /> timely Notice of the event and its effect on Contract Time and Contract Sum as required <br /> herein. <br /> Contractor shall in no event be entitled to a Contract Claim or adjustment of Contract Sum or <br /> Contract Time based on an allegation that the pre-existing subsurface or latent physical <br /> conditions at the site differing materially from those indicated in this Contract unless <br /> Contractor establishes that it reasonably relied on the conditions indicated in this Contract <br /> when making its bid, that the actual conditions encountered on the site differed materially from <br /> those indicated in this Contract, and that such materially-different conditions were not <br /> foreseeable at the time of its bid. <br /> 111 SECTION 1-05 CONTROL OF WORK <br /> 1-05.1 Authority of the Engineer <br /> Delete 1-05.1 and substitute the following: <br /> 1-05.1 City <br /> The City, and the City's Representative, shall have the authority to act as the sole judge of the <br /> Work and materials with respect to both quantity and quality as set forth in the Contract. It is <br /> expressly stipulated that the Plans, Specifications and other Contract Documents set forth the <br /> requirements as to the nature of the completed Work and do not purport to control the method of <br /> performing Work except in those instances where the nature of the completed Work is dependent <br /> on the method of performance. <br /> The City has the authority to act, do, perform, and make all decisions and actions authorized by <br /> the Contract Documents, including, but not limited to, Change Orders, progress payments, contract <br /> decisions, acceptability of the Contractor's Work, and early possession. The City has the authority <br /> to accept or reject requests for progress payments that have been submitted by the Contractor <br /> and recommended by the City's Representative. The City has the authority to make <br /> determinations of the acceptability of the Work. The City also has the authority to accept or reject <br /> the City's Representative's recommendations regarding retention of defective Work. <br /> 1-05.2 Authority of Assistants and Inspectors <br /> Delete 1-05.2 and substitute the following: <br /> I <br /> POE Combined Sewer Main Imp. Division 1 —GENERAL REQUIREMENTS October 2021 <br /> Work Order#UP3768 SP 1-23 <br />