INTERWEST — EVERETT CONTRACTOR'S YARD INTERIM FILL PROJECT Sitts & Hill Engineers, Inc. <br />CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN Job Number 17,733 <br />Section 8 — Construction Schedule and Phasing <br />The Contractor will coordinate all scheduling needed for the proposed construction. We anticipate <br />starting work as soon as permits are issued. The proposed work is the first phase of the development of <br />the site as a contractor's yard. <br />The following typical construction sequence will be used: <br />1. Flag or otherwise mark the limits of construction. <br />2. Post sign with name and phone number of supervisor. <br />3. Install erosion control measures where required as indicated on the construction plans. <br />4. Maintain erosion control measures in accordance with the manufacturer's recommendations <br />during construction and throughout interim fill condition of the site. <br />5. Remove all temporary BMPs only after final, permanent surfacing is established. <br />SITTS & HILL ENGINEERS, INC. 20 <br />TACOMA, WASHINGTON <br />