0132 16 <br /> Construction Progress Schedule <br /> PART 1-GENERAL <br /> ' 1.01 CONSTRUCTION SCHEDULE <br /> A. The Contractor shall prepare a construction schedule showing all tasks required to perform the Work. <br /> Schedule shall show all tasks performed by all trades that is required to perform work within the Contract <br /> Time. The Schedule shall include sufficient time for cleaning, punch list review and completion of punch list <br /> items prior to the designated physical completion date. <br /> ' 1.02 FORMAT <br /> A. The Schedule shall be a critical path method Gantt chart style. <br /> B. The Schedule shall clearly identify all Work and detailed to show specific steps to perform Work. The <br /> relationship between the work items shall show the starting date, length of time required to perform Work, <br /> completion of the work within the time frame shown. <br /> C. All Work found on the schedule of values shall be clearly identified. Unless otherwise expressly authorized <br /> in writing by the Owner's representative,the Contractor must integrate the schedules with the Schedule of <br /> Values and unit price items so that each construction activity is represented by a dollar value. <br /> D. Submittals dates shall be included and the relationship between submittal and the work item shall be <br /> identified <br /> E. Materials requiring long lead times shall be clearly identified on the schedule. This shall include: <br /> 1. Date materials musts be ordered <br /> ' 2. Time for manufacturing <br /> 3. Time for delivery <br /> 4. Delivery date(expected date materials to be at the project) <br /> ' 5. Date of Installation <br /> 1.03 SUBMITTAL <br /> A. At the pre-construction meeting,a preliminary schedule is required to be submitted. Once the preliminary <br /> schedule has been approved,the schedule shall become the Project Schedule. The Project Schedule,as <br /> approved by the Owner,will be an integral part of the contract and will establish interim completion dates for <br /> ' the various activities under the contract. <br /> B. Schedule shall be submitted electronic. Acceptable format.mmp <br /> c. Review by the Owner or Owner's Representative shall not constitute approval or acceptance of the <br /> Contractor's construction means, methods,sequencing, logic,order,precedence and succession of activities <br /> or Contractor's ability to complete the Work in a timely manner. <br /> D. The review/approval of any schedule shall not transfer any of the Contractor's responsibilities to the Owner. <br /> E. Subcontractors shall review all schedules prior to submittal. At the Owner's option and sole discretion, <br /> Owner may require Contractor to obtain written acceptance of each schedule by subcontractors as practical <br /> and feasible,as the schedule relates to subcontractors'work. <br /> 1.04 UPDATES <br /> A. The Project Construction Schedule will be reviewed and updated at each progress meeting. All changes to <br /> the project schedule of more than three(3)working days shall be documented. The Schedule shall be <br /> ' updated to show measures required to bring project back on schedule. The Contractor alone shall remain <br /> responsible for adjusting forces,equipment,and work schedules to ensure completion of the work within the <br /> Contract Time.Any mistakes or errors in any schedule,including, but not limited to, mistakes or errors of <br /> logic,order, precedence,and duration,are and remain the Contractor's. <br /> Rotary Park Renovation 1 of 2 <br />