My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
Sound Cleaning Resources Inc. 2/3/2022
>
Contracts
>
Small Works
>
Sound Cleaning Resources Inc. 2/3/2022
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
3/4/2022 10:23:46 AM
Creation date
3/4/2022 10:23:42 AM
Metadata
Fields
Template:
Contracts
Contractor's Name
Sound Cleaning Resources Inc.
Approval Date
2/3/2022
Department
Facilities
Department Project Manager
Doug Acheson
Subject / Project Title
Fire Station 4 Gutter & Downspout Replacement
Tracking Number
0003084
Total Compensation
$3,738.98
Contract Type
Small Works
Retention Period
6 Years Then Destroy
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
2
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
MIN <br /> CHANGE ORDER# <br /> EVERETT 0002 <br /> WAS HiNCTON <br /> Project(Procurement) Number: Small Works Roster Project Title: <br /> SWR 2021-098 - FIRE STATION 4 GUTTER AND DOWNSPOUT REPLACEMENT <br /> Description of Change: (Attach contractor's change proposal and cost schedule) (Attach Price or <br /> Cost Analysis) <br /> BUILDING/LOCATION: 5920 Glenwood Avenue, Everett WA 98203. <br /> installation of approximately 95' of snow stops along the south side of Fire Station 4 where <br /> previously installed gutters collapsed during a December 2021 cold weather event. Installation of <br /> snow stops along this portion of the building was not included in the initial contracted scope of work <br /> because this section of gutters was not determined to be vulnerable based on previous snow events. . <br /> It was not until the December 2021 snow event that the need for snow stops in this section was <br /> identified. Installed snow stops will alleviate future cold weather events having an adverse effect on <br /> any installed gutters, See attached quote for estimate of work required by change order. <br /> Time extended due to delays caused by the December 2021 cold weather event. <br /> The changes described above result in the following adjustments)in price and contract time (in calendar days). 1, <br /> Completion <br /> *Total Project Price Prior to this Change $28 765.40 Contract Time&Completion Date Prior 75 Date Prior <br /> to This Change 01/16/22 <br /> *Net(Increase)or(Decrease)Resulting from Net(increase)or(Decrease)Resulting <br /> this Change+ 8,738.98 from this Change 90 <br /> Completion <br /> I g $37 50 .40 Contract Time&Completion Date 165 Date After <br /> "Total Project Price includin this Change , Including This Change 04/16/22 <br /> By signing below, City of Everett and the Contractor agree that the Contract work shall be changed to the extent <br /> described in the above "Description of Change" and that the compensation shown above represents complete <br /> compensation for all such changes, including all direct and indirect costs and impacts. The City of Everett and the <br /> Contractor further agree that Contract time shall be adjusted to the extent shown above. This Change Order only <br /> changes the contract between City of Everett and the Contractor to the extent explicitly provided in this Change Order. <br /> CONTRACTOR CITY OF EVERETT <br /> • <br /> Sound Cleaning Resources Inc. City of Everett <br /> PO Box 37 3200 Cedar Street <br /> Issaquah,WA 98027 Everett,WA 98201 Date <br /> Project Manager: t� �"`"�- i/Z7' <br /> Z7a4Fe. 5' e&ha Division Manager: (" s ar 0/ / 2.. <br /> Department Director: Bobo <br /> l� <br /> Name&Title: Dakota Combaltc,Account Executive City Attorney <br /> Date: 1/19/2022 Mayor: assie Fr1//f/ZZ <br /> *WA Use Tex on materials Included, WAG 458-20-171 <br />
The URL can be used to link to this page
Your browser does not support the video tag.