Project: POE Combined Sewer Main Improvements <br /> Change Order No. 1 <br /> Change Order Effective Date: April 11, 2022 <br /> Contractor and City agree as follows: <br /> 1. The scope of Work shall be changed to the extent described in Exhibit A. <br /> 2. In full and complete compensation for the changes described in Exhibit A, <br /> including all direct and indirect costs and impacts, the contract price shall be <br /> adjusted as described in this Change Order. <br /> 3. The duration of the Contract shall be adjusted to the extent described in this <br /> Change Order. <br /> 4. Contractor waives and releases any and all claims arising out of, or related to, <br /> this Change Order, the work described in Exhibit A, and all work and actual or <br /> constructive changes that occurred or began prior to the date of this Change <br /> Order, including, but not limited to, claims for equitable adjustment of time and <br /> compensation, delay, impact, overhead, or inefficiencies. This provision does <br /> not apply to requests for equitable adjustment of time or price for which the <br /> Contractor timely and properly provided notice of a differing site condition, <br /> protest, dispute, claim or Contract Claim as required by the Contract <br /> Documents. If the Contract Documents establish a time period for notice of a <br /> differing site condition, protest, dispute, claim, or Contract Claim that ends after <br /> the date of this Change Order, but relates to work performed prior to the date of <br /> this Change Order, then this provision does not apply if the Contractor timely <br /> and properly submits such notice <br /> 5. This Change Order only changes the contract between Contractor and City to <br /> the extent explicitly provided herein. <br />