State of Washington Department of Ecology <br />Agreement No: WQC-2022-EverPW-00085 <br />Project Title: Water Quality Treatment at 3rd Avenue SE <br />Recipient Name: City of Everett <br />SCOPE OF WORK <br />Task Number: 3 Task Cost: $171,714.00 <br />Task Title: Design Plans and Specifications <br />Page 12 of 44 <br />Task Description: <br />The RECIPIENT shall ensure the following items are completed and provide the associated deliverables to ECOLOGY. The <br />RECIPIENT must approve all materials prior to submitting them to ECOLOGY for acceptance. <br />A. The RECIPIENT will develop a stormwater project design. The design submittals must conform to the Design Deliverables <br />for Stormwater Projects with Ecology Funding (Design Deliverables Document). Projects must be designed in accordance with <br />the Stormwater Management Manual for Eastern Washington, Stormwater Management Manual for Western Washington, or <br />equivalent manual. Refer to the ECOLOGY website for specific guidance. Project must be reviewed and accepted in writing <br />by ECOLOGY to be eligible for reimbursement. <br />The RECIPIENT will upload the design submittals listed below to EAGL for ECOLOGY review. Reduce design figures to <br />11x17 inches in size and ensure they are legible. <br />1. The RECIPIENT will submit a Design Report to ECOLOGY for review and acceptance. Allow 45 calendar days for <br />ECOLOGY review. <br />The RECIPIENT agrees to respond to ECOLOGY comments. The RECIPIENT must receive an Ecology Design Report <br />Acceptance Letter prior to proceeding to 90 Percent Design. <br />2. The RECIPIENT will submit a 90 Percent Design Package to ECOLOGY for review and acceptance. At a minimum, <br />this package must include 90 percent plans, specifications, engineer's opinion of cost, which includes a schedule of eligible <br />costs, and project construction schedule. The current required bid inserts and specifications may be found on the Ecology <br />website. Allow 45 calendar days for ECOLOGY review. <br />The RECIPIENT agrees to respond to ECOLOGY comments. The RECIPIENT must receive an Ecology 90 Percent Design <br />Acceptance Letter prior to proceeding Final Design. <br />3. The RECIPIENT will submit a Final Bid Package to ECOLOGY for review and acceptance prior to advertising the <br />project. The Final Bid Package includes: project plans, specifications, engineer's opinion of cost including a schedule of eligible <br />costs, and project construction schedule. Allow 15 calendar days for ECOLOGY review. <br />B. The RECIPIENT will calculate and submit a preliminary equivalent new/re-development area for the completed retrofit <br />project(s) using the methods outlined in the Design Deliverables Document. <br />C. The RECIPIENT will submit a preliminary GIS compatible project area in shapefile, geodatabase file, or <br />ECOLOGY -approved equivalent. The project area should include polygon features for stormwater facilities and contributing <br />areas. <br />Template Version 12/10/2020 <br />