Laserfiche WebLink
City of Everett 01 11 00 - 1 <br /> Inductive Charging Infrastructure for Everett Transit <br /> SECTION 01010 -SUMMARY OF WORK <br /> PART 1 -GENERAL <br /> 1.1 SUMMARY <br /> rA. This Work consists of the installation of owner furnished wireless charging system <br /> including inductive coils and charging cabinets as shown on the Contract Drawings <br /> and described in these Specifications, including all associated facilities. <br /> ' B. The contractor shall coordinate with Everett Transit and Momentum Dynamics to <br /> confirm the location of each inductive charging coil with the Gillig bus' s receiving <br /> pad prior to installation. <br /> C. The contractor shall furnish and install a main service switchboard, panelboard, <br /> conduit/ductbank, raceway and cables. Cables between the charging cabinets and <br /> inductive charging coils will be provided by Momentum Dynamics and installed by <br /> the Contractor. Momentum Dynamics will terminate the cables. <br /> ' D. The contractor shall provide and install all bonding and grounding as shown and <br /> noted on the Contract Drawings. <br /> E. The contractor shall provide and install bollards to protect the electrical panels and <br /> charging cabinets as shown on the Contract Drawings. <br /> ' F. The contractor shall coordinate with the local electric utility, Snohomish PUD, for <br /> service connection requirements. <br /> G. The contractor shall do the electrical testing and work with the inductive charger <br /> ' manufacturer who will conduct the field testing and final acceptance testing of the <br /> wireless charging system. <br /> ' H. The contractor shall be responsible for all permit applications including permit fee. <br /> 1.2 WORK SEQUENCE: The Contractor may mobilize on site or occupy staging areas if <br /> ' specifically approved by the Owner and if proper permits are in place. Notify the <br /> Construction Manager a minimum of two weeks prior to commencing mobilization at the <br /> site. During the construction period the Contractor shall have full use of the premises for <br /> construction operations pursuant to the restrictions listed in the following Special <br /> Provisions: <br /> A. Time of Completion and Schedule Milestones <br /> B. Access and other Restrictions. <br /> ' 1.3 OWNER FURNISHED MATERIALS: The Contractor shall review shop drawings, product <br /> data, and samples and inform the Owner of any discrepancies or problems anticipated in <br /> use of the product. <br /> 01 11 00 - 1 SUMMARY OF WORK <br /> I <br />