1 <br /> CITY OF EVERETT SPECIAL PROVISIONS <br /> shall require such Subcontractor, manufacturer, supplier or person to perform the <br /> specified action. <br /> ' 1-08.3 Progress Schedule <br /> 1-08.3(1) General Requirements <br /> ' Delete 1-08.3(1) and substitute the following: <br /> 1-08.3(1) General <br /> ' Because time is of the essence, diligent and expeditious progress and completion of the <br /> Work by the Contract Completion Date is required of the Contractor. Careful, adequate, <br /> accurate and complete planning and scheduling of the Work by the Contractor, both prior <br /> to the start of, and throughout, construction, is vital to the success of this Project for both <br /> the Contractor and the City. The purposes of the schedules and reports include: <br /> 1. Ensuring adequate planning and execution of the Work by the Contractor. <br /> ' 2. Assisting the City or its representative in monitoring construction. <br /> 3. Assessing the impact of any actual, potential or proposed change, including, <br /> but not limited to, the financial impact resulting from schedule changes and <br /> ' changes to the scope of Work. <br /> 4. Supporting the basis for construction payments. <br /> 5. Planning by City and tenants. <br /> 6. Avoiding additional or extra costs or expenses to the City. <br /> All schedules will be reviewed by the City and the City's Representative. The City or <br /> City's Representative's review of any schedule shall not transfer the Contractor's <br /> ' responsibilities to the City. Review shall not constitute approval or acceptance of the <br /> Contractor's construction means, methods, sequencing, logic, order, precedence and <br /> succession of activities or Contractor's ability to complete the Work in a timely manner. <br /> ' Any mistakes or errors in any schedule, including, but not limited to, mistakes or errors <br /> of logic, order, precedence, and duration, are and remain the Contractor's. The City or <br /> City's Representative may, however, comment upon the schedule. The Contractor <br /> remains wholly responsible for completing the Work within the Contract duration. Any <br /> comments by City or City's Representative personnel regarding the schedule shall not <br /> be construed as approval or ratification, nor shall the Contractor incorporate or change <br /> its schedule as a result of City or City's Representative comments in the absence of an <br /> express written directive to that effect. <br /> Contractor shall submit, update and maintain schedules as required by the Contract <br /> Documents. <br /> The Contractor shall provide sufficient material, equipment, and labor to meet the interim <br /> milestones, Substantial Completion, Physical Completion and Completion Dates <br /> ' provided by the Contract Documents. The City allocates its resources to a Contract <br /> based on the total time allowed in the Contract. The Contractor may submit a schedule <br /> indicating Completion Date earlier than the end of Contract Time, but City cannot <br /> guarantee its resources will be available to meet such schedule. City shall not pay or be <br /> liable for any additional compensation if the Contractor is not able to meet a schedule <br /> that indicates a Completion Date earlier than the end of Contract Time. <br /> Failure to schedule City furnished or installed materials and Equipment for installation <br /> ' on or after its planned arrival pursuant to the City's Contract with the supplier or failure <br /> to notify the City in writing of tasks dependent upon the fact or date of arrival of such <br /> City furnished materials and Equipment, constitute a waiver by Contractor of any <br /> ' Contract Claim arising out of or related to the timeliness of the furnishing or installation <br /> Water Main Replacement"W" Division 1 —GENERAL REQUIREMENTS April, 2022 <br /> WO No.—UP3766 SP—93 <br />