CITY OF EVERETT SPECIAL PROVISIONS <br /> of the Work, or extend the duration of the critical path of the schedule. Upon such <br /> determination, the City's Representative will make an adjustment of Contract Sum or <br /> Contract Time, as appropriate. Extensions of Contract Time will be evaluated in <br /> accordance with 1-08.3 PROGRESS SCHEDULE. <br /> The City's Representative's determination that differing site conditions do not exist <br /> and/or the appropriate adjustment in Contract Sum or Contract Time (if any) shall be <br /> final. If there is a decrease in the cost or time required to perform the Work, failure of <br /> the Contractor to notify the City's Representative of the differing site condition shall not <br /> affect the City's right to make an adjustment in the Contract Sum or Contract Time. <br /> Additionally, no Contract Claim or adjustment of Contract Sum or Contract Time shall be <br /> allowed unless the Contractor has followed the procedures provided for in this Contract, <br /> including, but not limited to, furnishing timely Notice of the event and its effect on <br /> Contract Time and Contract Sum as required herein. <br /> Contractor shall in no event be entitled to a Contract Claim or adjustment of Contract <br /> Sum or Contract Time based on an allegation that the pre-existing subsurface or latent <br /> physical conditions at the site differing materially from those indicated in this Contract <br /> unless Contractor establishes that it reasonably relied on the conditions indicated in this <br /> Contract when making its bid, that the actual conditions encountered on the site differed <br /> materially from those indicated in this Contract, and that such materially-different <br /> conditions were not foreseeable at the time of its bid. <br /> 1-05 CONTROL OF WORK <br /> 1-05.1 Authority of the Engineer <br /> Delete 1-05.1 and substitute the following: <br /> 1-05.1 City <br /> (******) <br /> The City, and the City's Representative, shall have the authority to act as the sole judge of <br /> the Work and materials with respect to both quantity and quality as set forth in the Contract. <br /> It is expressly stipulated that the Plans, Specifications and other Contract Documents set <br /> forth the requirements as to the nature of the completed Work and do not purport to control <br /> ' the method of performing Work except in those instances where the nature of the completed <br /> Work is dependent on the method of performance. <br /> The City has the authority to act, do, perform, and make all decisions and actions authorized <br /> ' by the Contract Documents, including, but not limited to, Change Orders, progress payments, <br /> contract decisions, acceptability of the Contractor's Work, and early possession. The City <br /> has the authority to accept or reject requests for progress payments that have been submitted <br /> by the Contractor and recommended by the City's Representative. The City has the authority <br /> to make determinations of the acceptability of the Work. The City also has the authority to <br /> accept or reject the City's Representative's recommendations regarding retention of defective <br /> Work. <br /> 1-05.2 Authority of Assistants and Inspectors <br /> Delete 1-05.2 and substitute the following: <br /> 1-05.2 City's Representative <br /> The City's Representative shall be satisfied that all the Work is being done in accordance <br /> with the requirements of the Contract. The Contract and Specifications give the City's <br /> Representative authority over the Work. Whenever it is so provided in this Contract, the <br /> decision of the City's Representative shall be final. <br /> Water Main Replacement"W" Division 1 -GENERAL REQUIREMENTS April,2022 <br /> WO No.-UP3766 SP-57 <br /> I <br />