City of Everett 00 72 00 - 23 <br /> I <br /> 6. Altering facilities,Equipment,materials,services,or sites,provided by the Owner,and <br /> ' 7. Ordering the Contractor to accelerate or Delay Work. <br /> If the Contractor and Owner do not agree upon scope of Work changed or adjustment to the Contract Sum <br /> and Contract Time,the Owner may,at its sole option,unilaterally direct the Contractor to implement any <br /> change by notice. The Owner shall not pay or be responsible or liable for any change implemented by the <br /> Contractor without explicit notice from the Owner to proceed. <br /> 6.2 EXTRA WORK <br /> At its sole option,the Owner may(1)perform Extra Work itself,(2)employ others to do it,(3)direct the <br /> Contractor to perform the Extra Work at existing unit bid price,(4)direct the Contractor to perform the <br /> Extra Work at a mutually agreed upon price,or(5)direct the Contractor to perform the Extra Work on a <br /> Force Account basis. <br /> 6.3 CHANGE ORDERS <br /> ' Changes to the Work may result in an increase or decrease in Contract Sum,as provided in 9.2. <br /> PAYMENT FOR CHANGES.Requests for an increase in Contract Time must be made as provided in <br /> 5.2.2.2 Extensions of Contract Time, as applicable. Substantial changes in Contract Time,Contract <br /> Sum or Work will often be negotiated and agreed between the Contractor and Owner before the Owner <br /> directs the Contractor to proceed with the change. <br /> If the Contractor and Owner agree on the scope of Work and any changes to Contract Sum and Contract <br /> Time,the Contractor and Owner shall execute an agreed Change Order. However,if the Contractor and <br /> Owner do not agree, the Owner may,in its sole discretion,issue a unilateral Change Order changing the <br /> scope of Work and making any adjustments to the Contract Sum pursuant to 9.2.PAYMENT FOR <br /> ' CHANGES and Contract Time in such amount and for such time as the Owner thinks appropriate. <br /> Contractor agrees to use the agreed and unilateral Change Order forms included in the Contract <br /> Documents or otherwise provided by Owner. The Contractor accepts all requirements,terms and <br /> conditions of a Change Order by: signing it; writing a separate acceptance;or by failing to notify the <br /> Owner immediately in writing that Contractor disagrees with the Change Order and does not intend to be <br /> bound by its terms. <br /> The Contractor waives all Contract Claims with respect to(and is estopped from denying its agreement <br /> with)any unilateral Change Order for which the Contractor does not immediately give Notice to the <br /> Owner as provided in ARTICLE 10.NOTICE TO OWNER and submit a Contract Claim as provided <br /> in ARTICLE 12.CONTRACT CLAIMS. A unilateral Change Order that is not timely protested as <br /> provided in this section shall be full payment and final settlement of all asserted and unasserted Contract <br /> Claims for Contract Time and all costs of any kind,including costs of Delays, inefficiencies and impacts, <br /> related to,arising out of,or resulting from,any Work described in the Change Order. <br /> ' The Contractor shall obtain written consent of the surety or sureties if the Owner's Representative <br /> requests such consent. <br /> 6.4 VALUE ENGINEERING AND COST SHARING <br /> The Contractor may submit proposals for changing the Drawings,Specifications,or other requirements of <br /> the Contract Documents and the Owner,in its sole discretion,may accept or reject such proposals. If <br /> accepted by the Owner and if the proposal decreases the direct,actual costs of constructing the Work,the <br /> Contract Sum shall be reduced by fifty percent(50%)of the direct,actual construction cost saved. <br /> Because the Owner has the sole discretion whether to consider,accept or reject the Contractor's proposal <br /> and the Contractor has no right to require the Owner to consider or accept such proposals,the Owner's <br /> decision is not reviewable by any court. This subsection applies only to change proposals initiated solely <br /> by the Contractor(or its Subcontractors and Suppliers)and does not apply to change proposals requested <br /> or initiated by the Owner or the Owner's Representative. The Owner is not obligated or required to <br /> consider any Contractor initiated change proposals and may,in its sole discretion,refuse to do so. Under <br /> 00 72 00 - 23 GENERAL CONDITIONS <br />