EVERETT <br /> WASHINGTON <br /> Change Order Cover Sheet/For Internal City Use Only <br /> CONTRACT TIME <br /> Original Contract Duration Working Days U Calendar Days Z Days <br /> Date of Notice to Proceed 1/31/2022 <br /> Cumulative adjustment to duration by prior Change Orders 0 <br /> Adjustment to duration by this Change Order 94 <br /> New Contract Duration (including this Change Order) 184 Days <br /> EXPLANATION/JUSTIFICATION <br /> Change Order No. One contains a list of additional work that is required to: <br /> (a) Correct unforeseen conditions in the existing site and building. <br /> (b) Correct oversights in the original plans and specifications. <br /> (c) Comply with codes or rulings of building officials and building inspectors. <br /> (d) Improve the quality of appearance and performance of the site. <br /> City Staff Contact: Brad Chenoweth 425-308-3939 <br /> Date: 9/13/2022 <br />