DIVISION 01000 GENERAL REQUIREMENTS <br />01000 GENERAL NOTES <br />PART 1 - GENERAL <br />A. DRAWINGS AND SPECIFICATIONS ARE INTENDED TO BE <br />COMPLIMENTARY. SPECIFIC INFORMATION MAY BE FOUND IN EITHER OR <br />BOTH. <br />B. BIDDING CONTRACTORS SHALL INCLUDE ALL LABOR, MATERIALS, <br />SCAFFOLDING, CRANES, EQUIPMENT FASTENERS ELC. NECESSARY FOR <br />COMPLETION AND FINAL COMPLETE TURNOVER OF AN OPERATIONAL RETAIL <br />FACILITY. <br />C. THE TENANT HAS INDICATED AN INTENTION TO USE AMERICAN <br />INSTITUTE OF ARCHITECTS DOCUMENT A-107 "GENERAL CONDITIONS OF THE <br />CONTRACT FOR CONSTRUCTION" AS PART OF THE CONTRACT DOCUMENTS <br />FOR THIS WORK. <br />D. ALL PERSONS INTENDING TO PROVIDE GOODS OR SERVICES IN <br />CONNECTION w/THE WORK ARE ADVISED TO READ AND UNDERSTAND THE <br />APPLICABLE ADA DOCUMENTS PRIOR TO PROCEEDING. <br />F. THE TENANT HAS AWARDED SEPARATE CONTRACTS FOR SOME <br />CONSTRUCTION WORK THAT WILL BE CONDUCTED SIMULTANEOUSLY WITH <br />WORK UNDER THIS CONTRACT. GENERAL CONTRACTOR MUST COOPERATE <br />WITH ALL OTHER CONTRACTORS SO THAT WORK UNDER THOSE CONTRACTS <br />MAY BE CARRIED OUT SMOOTHLY, WITHOUT INTERFERING WITH, OR DELAYING <br />WORK UNDER THIS CONTRACT. <br />F. PRIOR TO START OF CONSTRUCTION, GENERAL CONTRACTOR SHALL <br />ARRANGE A MEETING WITH LANDLORD'S CONSTRUCTION REPRESENTATIVE TO <br />REVIEW AND ESTABLISH ALL LANDLORD REQUIREMENTS. THIS INCLUDES, BUT IS <br />NOT LIMITED TO, THE FOLLOWING: ALL CONSTRUCTION, SCHEDULES, <br />WORKMAN PARKING, DELIVERY AND STORAGE OF MATERIALS, SAFETY <br />PROTECTION, TRASH REMOVAL, SECURITY, AND DOCUMENTS REQUIRED FOR <br />FINAL LANDLORD SIGN -OFFS. GENERAL CONTRACTOR IS TO NOTIFY TENANT'S <br />CONSTRUCTION MANAGER IMMEDIATELY OF ANY ITEM THAT MAY AFFECT THE <br />DESIGN INTENT OF THE DRAWINGS, OR RESULT. <br />G. ANY ITEMS DIRECTED BY LANDLORD, INSPECTORS, OR ANY OTHER <br />AUTHORITY THAT AFFECTS THE DESIGN INTENT OF THE DRAWINGS, OR <br />RESULTS IN ADDITIONAL COSTS OR SCHEDULE DELAYS SHOULD NOT BE <br />PERFORMED UNTIL RECEIPT OF APPROVAL BY TENANT'S CONSTRUCTION <br />MANAGER. ALL CHANGES MUST IMMEDIATELY BE SUBMITTED IN WRITING TO <br />TENANT'S CONSTRUCTION MANAGER FOR REVIEW. SUBMISSION SHALL <br />INCLUDE A GENERAL DESCRIPTION OF THE WORK REQUESTED, SIGNED BY THE <br />REQUESTING AUTHORITY. IN ADDITION, SUBMISSION MUST INCLUDE A LABOR <br />AND MATERIAL COST BREAKDOWN AND THE IMPACT TO THE CONSTRUCTION <br />SCHEDULE. <br />01005 CONTRACTORS USE OF THE PREMISES. <br />PART 1 - GENERAL <br />A. THE GENERAL CONTRACTOR AND ALL CONTRACTORS BIDDING ON THIS <br />PROJECT SHALL VISIT THE JOB SITE TO FAMILIARIZE THEMSELVES WITH ACTUAL <br />JOB CONDITIONS AND TO CHECK FOR ANY INTERFERENCE BETWEEN THEIR <br />WORK AND THAT OF OTHER TRADES AND/OR APPARENT VIOLATIONS OF <br />LOCAL, STATE, OR FEDERAL CODES, LAWS, ORDINANCES, AND REGULATIONS <br />BEFORE ENTERING INTO A CONTRACT WITH EITHER THE GENERAL <br />CONTRACTOR AND/OR TENANT. <br />1. ALL ITEMS SHALL BE INCLUDED IN THE BASF_ BID TO ACHIEVE THE FINAL <br />PRODUCT INDICATED IN DRAWINGS. THIS INCLUDES, BUT IS NOT LIMITED TO, <br />THE FOLLOWING: CONCRETE FLOOR PREP, FLOOR SLAB X-RAYING, DEMISING <br />WALL GYPSUM BOARD EXTENT AND CONDITION, REQUIRED FIRE PROOFING, <br />ELECTRICAL PANELS, ELECTRICAL, WATER, SEWER, VENTS AND TELEPHONE <br />CONDUITS, ANY LANDLORD REQUIRED FIRE PROTECTION SYSTEM OR TIE-INS <br />TO BLDG. MANAGEMENT SYSTEMS, FIRE EXTINGUISHERS, AND STRUCTURAL <br />REQUIREMENTS FOR TENANT'S EQUIPMENT. <br />2. GENERAL CONTRACTOR SHALL NOTIFY THE ARCHITECT AND TENANT IN <br />WRITING BEFORE ENTERING INTO A CONTRACT WITH THE TENANT IF ANY <br />INTERFERENCE OR VIOLATIONS APPEAR AND DEPARTURE FROM THE DESIGN <br />INTENT OF THE DOCUMENTS IS REQUIRED. <br />3. FAILURE TO PROVIDE ARCHITECT AND TENANT'S CONSTRUCTION <br />MANAGER WITH THE AFOREMENTIONED NOTIFICATION SHALL RESULT IN THE <br />GENERAL CONTRACTOR BEING HELD RESPONSIBLE TO COMPLETE ALL WORK <br />REQUIRED TO MEET THE DESIGN INTENT OF THE CONTRACT DOCUMENTS AT <br />HIS/HER OWN COSTS WITH NO ADDITIONAL EXPENSES (EXTRAS) BEING <br />INCURRED BY THE TENANT, EXTRAS WILL NOT BE ALLOWED FOR JOB SITE <br />CONDITIONS THAT WERE READILY VISIBLE OR DETERMINED. <br />4. ALL SUB TRADES SHALL COORDINATE THEIR WORK WITH THE WORK OF <br />OTHERS OR WITH EXISTING CONDITIONS OCCURRING ABOVE OR BELOW THE <br />LEASED PREMISES AND SHALL MAKE CHANGES FROM TIME TO TIME AS <br />REQUESTED TO ACCOMMODATE SUCH WORK OR CONDITIONS AT NO CHARGE <br />TO TENANT. <br />5. CONTRACTORS SIGNS OR SIGNS OF ANY KIND MAY NOT BE DISPLAYED <br />ON BARRICADES <br />6. THE G.C. SHALL BUILD ON SITE A TEMPORARY LOCKABLE STORAGE AREA. <br />G.C. SHALL ACCEPT ALL TENANT SUPPLIED ITEMS AND STORE THEM SAFELY IN <br />SUCH SPACE. <br />A. LAYOUT OF WORK <br />1. IMMEDIATELY AFTER DEMOLITION, GENERAL CONTRACTOR TO <br />ADVISE TENANT OF ANY DISCREPANCIES IN OVERALL WIDTH, LENGTH, <br />AVAILABLE CEILING HEIGHTS, COLUMN LOCATIONS, STOREFRONT, UTILITY <br />LOCATIONS, ETC - <br />2. EXERCISE PROPER PRECAUTION TO VERIFY ALL EXISTING <br />CONDITIONS AND LAYOUT OF CONTRACTOR TO NOTIFY TENANT OF ANY <br />DISCREPANCIES IMMEDIATELY. CONTRACTOR IS RESPONSIBLE FOR ANY <br />ERROR RESULTING FROM FAILURE TO EXERCISE SUCH PRECAUTION. SUCH <br />ERROR WILL NOT BE CONSIDERED SUBSEQUENTLY AS A BASIS FOR EXTRA <br />COMPENSATION. <br />3. GENERAL CONTRACTOR IS TO LAYOUT WORK AND BE RESPONSIBLE <br />FOR ALL LINES, MEASUREMENTS OF THE BUILDING, UTILITIES, AND OTHER <br />WORK EXECUTED UNDER THE CONTRACT. <br />4. SHOULD A CONTRACTOR FIND DISCREPANCIES IN, OR OMISSIONS <br />FROM THE DRAWINGS OR SPECIFICATIONS, OR SHOULD HE BE IN DOUBT <br />AS TO THEIR MEANING, HE SHALL AT ONCE NOTIFY THE ARCHITECT AND <br />TENANT. <br />B. CODES AND STANDARDS <br />1, ALL WORK, MATERIALS, AND INSTALLATION SHALL BE IN STRICT <br />ACCORDANCE WITH ALL ORDINANCES, STATE AND LOCAL BUILDING <br />CODES, LATEST EDITION. SEE TITLE SHEET FOR SPECIFIC EDITIONS. <br />2. DESIGN LOADS: LOADS AND CODE RESTRICTIONS FOR ALL DESIGN <br />CONSIDERATIONS SHALL CONFORM TO THE LOCAL AND STATE CODES AND <br />ALL GOVERNING CODES. <br />A. TRASH REMOVAL <br />1. ALL TRADES SHALL CONFINE CONSTRUCTION WORK TO WITHIN LEASED <br />PREMISES AS MUCH AS POSSIBLE AND SHALL WORK IN AN ORDERLY MANNER <br />REMOVING TRASH AND DEBRIS FROM PROJECT ON A DAILY BASIS INCLUDING <br />TRASH AND DEBRIS GENERATED BY TENANT SUPPLIED AND/OR INSTALLED <br />ITEMS. AT NO TIME WILL PIPES, WIRES, BOARD, OR OTHER CONSTRUCTION <br />MATERIALS CROSS PUBLIC AREAS WHERE HARM COULD BE CAUSED TO THE <br />PUBLIC. <br />2. MALL DOORS ARE NOT TO BE PROPPED OPEN BY CONSTRUCTION <br />WORKERS AT ANY TIME. <br />3. THERE WILL BE NO STORAGE OF MATERIAL OR RUBBISH IN CORRIDORS <br />OR OTHER LANDLORD AREAS AT ANY TIME. IF DEBRIS IS FOUND IN THIS AREA, <br />IT WILL BE REMOVED AT THE EXPENSE OF THE GENERAL CONTRACTOR. <br />4. ALL SUB TRADES SHALL COORDINATE REMOVAL OF DEBRIS AND <br />GARBAGE GENERATED BY THEIR TRADES WITH THE G.C. <br />S. THE G.C. SHALL BE RESPONSIBLE FOR THE REMOVAL OF ALL DEBRIS <br />INCLUDING PACKAGING MATERIAL OF MILLWORK. <br />D. ROOF CUTTING AND PATCHING <br />1. CUTTING AND PATCHING FOR ALL ROOF OPENINGS SHALL BE <br />PERFORMED BY LANDLORDS ROOFING CONTRACTOR, IF SO REQUIRED BY THE <br />LANDLORD, ENGAGED AND PAID BY GENERAL CONTRACTOR. <br />2. THE LANDLORDS ROOFING CONTRACTOR WILL, AT SUBTRADES WRITTEN <br />REQUEST AND COST, PROVIDE THE OPENINGS, ANCHORING DEVISES, CURBS, <br />FLASHINGS, PATCHING, ETC., AS REQUIRED FOR TENANTS EQUIPMENT SO AS <br />TO MAINTAIN THE INTEGRITY AND GUARANTEE OF THE ROOF. ALL SUBTRADES <br />SHALL INCLUDE THE COST OF SUCH OPENINGS, ETC. IN THEIR PROPOSALS TO <br />TO THE GENERAL CONTRACTOR DURING BIDDING. SUBTRADES SHALL <br />COORDINATE WITH THE LANDLORD AND/OR ROOFING CONTRACTOR AND <br />ALSO REIMBURSE HIM FOR SAME. <br />3. ROOF REPAIRS OR PENETRATIONS REQUIRED BY REMOVAL OR <br />RELOCATION OF EXISTING EQUIPMENT OR INSTALLATION OF NEW EQUIPMENT <br />(CUTTING OF ROOF AND DECK MATERIAL AND/OR REPAIR OF THE SAME) SHALL <br />BE COORDINATED WITH THE LANDLORD'S REPRESENTATIVE. <br />F. DELIVERIES <br />1. GENERAL CONTRACTOR IS RESPONSIBLE FOR UNLOADING ALL TENANT <br />PROVIDED ITEMS AT THE JOB SITE INCLUDING A HEAVY AMOUNT OF <br />MILLWORK WHICH IS TENANT SUPPLIED. THESE TENANT SUPPLIED ITEMS SHALL <br />BE THE G.C.'S RESPONSIBILITY TO UNLOAD, STORE, AND DELIVER TO PROPER <br />STORE AREAS WHEN REQUIRED. SEE TITLE SHEET, "GENERAL NOTES", FOR <br />ADDITIONAL NOTES, PROCEDURES, AND RESPONSIBILITIES. <br />2. THE GENERAL CONTRACTOR IS RESPONSIBLE TO COORDINATE <br />ACCEPTABLE HOURS FOR DELIVERY AND LOCATION OF DELIVERY OF BUILDING <br />PRODUCTS AND TENANTS ITEMS WITH LANDLORD'S REPRESENTATIVE. <br />01041 PROJECT COORDINATION <br />PART 1 - GENERAL <br />A. ALL PROJECT COORDINATION SHALL BE THROUGH TENANT'S <br />CONSTRUCTION MANAGER AS LISTED ON TITLE SHEET. <br />B. COMPLY WITH CONSTRUCTION MANAGER'S PROCEDURES FOR <br />INTRA-PROJECT COMMUNICATIONS; SUBMITTALS, REPORTS AND RECORDS, <br />SCHEDULES, COORDINATION DRAWINGS, RECOMMENDATIONS; AND <br />RESOLUTION OF AMBIGUITIES AND CONFLICTS, INCLUDING REQUESTS FOR <br />SUBSTITUTIONS AND CHANGE ORDERS. <br />01200 PRICE, PAYMENT, AND CONTRACT <br />PART 1 - GENERAL <br />A. BIDDING CONTRACTORS SHALL PREPARE A BID, WHICH SHALL BE <br />SUBMITTED IN ACCORDANCE WITH INSTRUCTIONS TO BIDDERS CONTAINED <br />WITHIN BID DOCUMENT PACKAGE. <br />B. PAYMENT SCHEDULE FOR PROJECT WILL BE ON A MONTHLY SUBMITTAL <br />OF AIA DOCUMENT #G702 AND #G703 "APPLICATION AND CERTIFICATE FOR <br />PAYMENT" UNLESS OTHERWISE REQUESTED BY TENANT. <br />C. CONTRACT SHALL BE AIA DOCUMENT #A107 "STANDARD FORM OF <br />AGREEMENT BETWEEN OWNER AND CONTRACTOR <br />01400 QUALITY/GUARANTEE <br />PART 1 - GENERAL <br />A. ALL WORK SHALL BE EXECUTED BY LICENSED TRADESMEN AND <br />MECHANICS QUALIFIED, THROUGH EXPERIENCE_, IN THEIR RESPECTIVE TRADES. <br />SAID CONTRACTORS SHALL REMOVE AND REPLACE WITHOUT DELAY ANY <br />WORK CONTRARY TO THE CONTRACT DOCUMENTS WHEN SPECIFICALLY <br />DIRECTED. <br />B. GENERAL CONTRACTOR AND/OR SUB CONTRACTOR SHALL GUARANTEE <br />HIS WORKMANSHIP AND MATERIALS FOR A PERIOD OF ONE YEAR FROM DATE <br />OF ACCEPTANCE BY THE OWNER. <br />01426 PROCEDURES <br />PART 1 - GENERAL <br />A. ALL ITEMS SHALL BE INSTALLED USING STANDARD PROFESSIONAL <br />PRACTICES USING FASTENERS, ADHESIVES AND METHODS REQUIRED BY <br />MANUFACTURER AND INDUSTRY MANUALS. <br />01510 TEMPORARY UTILITIES <br />PART I - GENERAL <br />A. GENERAL CONTRACTOR TO VERIFY PROVISIONS FOR TEMPORARY <br />UTILITIES INCLUDING ELECTRICITY, LIGHTING, HEAT, VENTILATION, TELEPHONE <br />SERVICE, WATER AND SANITARY FACILITIES. G.C. TO INCLUDE A FULL TIME <br />PHONE AND FAX ON SITE CAPABLE OF INCOMING CALLS DURING ENTIRE <br />CONSTRUCTION PERIOD. <br />11542 CRANES AND HOISTS <br />'ART 1 - GENERAL <br />�. GENERAL CONTRACTOR AND/OR SUB -CONTRACTOR ARE RESPONSIBLE <br />AND SHALL INCLUDE IN THEIR BIDS ALL NECESSARY EQUIPMENT INCLUDING <br />.RAKES, HOISTS, SCAFFOLDING, PLATFORMS, ETC., REQUIRED FOR ERECTION <br />)F BUILDING COMPONENTS, EQUIPMENT AND ALL TENANT SUPPLIED ITEMS AS <br />OCATED ON PLANS. CONTRACTOR SHALL PAY ALL RELATED FEES, PERMITS, <br />TC. PROTECTION OF THE PUBLIC AND EXISTING IN -PLACE WORK IS THE <br />.ESPONSIBILITY OF THE GENERAL CONTRACTOR. <br />01700 CLEANING / ADJUSTING / MAINTENANCE / WARRANTIES <br />PART 1 - GENERAL <br />A. FINAL CLEANING <br />1. CONDUCT CLEANING AND REMOVE WASTE AND SURPLUS MATERIALS, <br />RUBBISH AND CONSTRUCTION DEBRIS FROM SITE TO COMPLY WITH LOCAL <br />LAW, ORDINANCE FEDERAL AND ENVIRONMENTAL AND ANTIPOLLUTION <br />REGULATIONS. <br />2. PROVIDE A PROFESSIONAL CLEANING SERVICE TO EXECUTE FINAL_ <br />CLEANING PRIOR TO TURN -OVER. <br />3. CLEAN EXPOSED EXTERIOR AND INTERIOR HARD -SURFACED FINISHED <br />TO A DIRTY -FREE CONDITION,FREE OF STAIN, FILMS, AND SIMILAR FOREIGN <br />SUBSTANCES. <br />4. REPLACE AIR FILTERS. <br />5. LEAVE PROJECT CLEAN AND READY FOR OCCUPANCY. <br />A. ADJUSTING <br />1. ADJUST OPERATING PRODUCTS AND EQUIPMENT TO ENSURE SMOOTH <br />AND UNHINDERED OPERATION. <br />C. OPERATION AND MAINTENANCE DATA <br />1. SUBMIT DATA BOUND IN 8-1/2x11 INCH TEXT PAGES, THREE D SIDE RING <br />BINDER WITH DURABLE PLASTIC COVERS. <br />2. PREPARE BINDER COVER WITH PRINTED TITLE "OPERATION AND <br />MAINTENANCE INSTRUCTIONS", WITH TITLE OF PROJECT, LOCATION AND DATE. <br />THE HARD COPY BINDER SHOULD BE RETAINED ON SITE FOR STORE <br />MANAGER'S USE, A COPY SHOULD ALSO BE SENT TO THE CONSTRUCTION <br />PROJECT MANAGER VIA EMAIL AS A FILE COPY. <br />D. WARRANTIES AND BONDS <br />1. EXECUTE AND ASSEMBLE TRANSFERABLE WARRANTY DOCUMENTS FROM <br />SUBCONTRACTORS, SUPPLIERS, AND MANUFACTURERS. <br />END OF DIVISION <br />DIVISION 02000 - SITE WORK <br />02060 BUILDING DEMOLITION <br />PART 1 - GENERAL <br />A. SELECTIVE DEMOLITION <br />1. THIS SECTION IS INCLUDED FOR GENERAL REFERENCE OF WORK TO BE <br />REMOVED BY THE GENERAL CONTRACTOR. <br />2. CONSULT DEMOLITION PLANS INCLUDED WITH PROJECT DOCUMENTS <br />FOR ADDITIONAL NOTES AND SITE SPECIFIC ITEMS. <br />3. DEMOLITION INCLUDES REMOVAL OF THE EXISTING INTERIORS, IF <br />REQUIRED, BUT NOT LIMITED TO INTERIOR PARTITIONS, CABINETS, SUSPENDED <br />CEILING TILE, ELECTRICAL, MECHANICAL, ETC., AS REQUIRED, AS SHOWN OR AS <br />DIRECTED. <br />4. ALL ITEMS INDICATED OR REQUIRED TO BE DEMOLISHED OR REMOVED <br />TO BE LEGALLY DISPOSED OF IN COORDINATION AND COMPLIANCE WITH ALL <br />LANDLORD PROCEDURES AND REGULATIONS. <br />5. GC TO COMPLY WITH ANY DEBRIS,/TRASH SEPARATION REQUIREMENTS IN <br />PLACE WITH LL, JURISDICTIONS, OR PROJECT REQUIREMENTS FOR CONSTRUCTION <br />WASTE MANAGEMENT AND DISPOSAL. <br />6. ALL ITEMS INDICATED TO BE RELOCATED OR REINSTALLED TO BE <br />CLEANED, SERVICED AND PREPARED FOR PROPER RE -USE. ANY ITEMS STORED <br />DURING CONSTRUCTION ARE TO BE PROTECTED TO AVOID DAMAGE OR THEFT <br />7. ALL ITEMS INDICATED AS EXISTING TO REMAIN, SHALL BE CLEANED, <br />SERVICED AND PREPARED FOR PROPER CONTINUED RE -USE. PROTECT ALL <br />ITEMS SUFFICIENTLY DURING CONSTRUCTION TO AVOID DAMAGE OR THEFT. <br />8. COOPERATE AND COORDINATE WITH LANDLORD, THE TENANTS OF THE <br />ADJACENT SPACES AND THE TENANT, IN SCHEDULING WORK IN ORDER TO <br />CAUSE THE LEAST INCONVENIENCE TO PERSONNEL AND PROPERTY. <br />9. SEE MECHANICAL AND ELECTRICAL PLANS FOR SPECIFIC DEMOLITION <br />ITEMS UNDER THOSE TRADES. <br />PART 2 - PREPARATION / EXECUTION <br />A. ARRANGE WITH THE LANDLORD A CONVENIENT TIME TO PERFORM <br />DEMOLITION WORK AND INSTALL TEMPORARY PROTECTED MEANS OF EGRESS <br />FROM REQUIRED EXITS. INCLUDE TEMPORARY LIGHTING AND SAFETY DEVICES, <br />ALL IN ACCORDANCE WITH GOVERNING STATE AND LOCAL CODES AND <br />LAND -LORD REQUIREMENTS. <br />B. THE CONTRACTOR SHALL REMOVE, REPAIR, RESTORE, AND REPLACE <br />WHERE ANY SUCH WORK IS NECESSARY OR AS INDICATED ON THE DRAWINGS. <br />CUT ALL NECESSARY OPENINGS, AND PATCH/REPAIR/SEAL SAME TO DEGREE <br />NECESSARY TO SATISFY ALL REQUIREMENTS. INSOFAR AS POSSIBLE, ALL <br />PROTRUSIONS, MARKS, CRACKS OR OTHER EVIDENCE OF A DEFICIENT OR <br />DAMAGED CONDITION SHALL BE ELIMINATED, UNLESS SPECIFICALLY NOTED <br />OTHERWISE. ANY PARTS WHICH ARE SPLIT, CRACKED, CHIPPED, SPALLED, <br />BROKEN, MISSING, OR OUT OF LINE OR ADJUSTMENT, MECHANICALLY OR <br />STRUCTURALLY UNSAFE OR UNSOUND, BENT, TORN OR OTHERWISE DEFICIENT <br />OR INJURED IN ANY MANNER, SHALL BE REMOVED, REPLACED, RESTORED OR <br />REPAIRED. LANDLORD'S REPRESENTATIVE, ARCHITECT, AND TENANT'S <br />CONSTRUCTION MANAGER MUST BE NOTIFIED IMMEDIATELY OF ANY <br />STRUCTURAL OR SAFETY DEFECTS, AND ONLY THE TENANT'S CONSTRUCTION <br />MANAGER IF THE DEFECTS) ARE LIMITED TO COSMETIC FINISHES. <br />C. EXERCISE EXTREME CARE DURING DEMOLITION SO AS NOT TO DAMAGE <br />OR DISRUPT ANY UTILITY OR SPRINKLER LINES WHICH MIGHT PASS THROUGH <br />THIS SPACE TO SERVICE OTHER MALL SPACES OR TENANTS. GENERAL <br />CONTRACTOR WILL BEAR SOLE RESPONSIBILITY OF ANY SUCH DISRUPTION OR <br />DAMAGE. <br />D. ALL ABANDONED ELECTRICAL_ AND TELEPHONE CONDUIT, PLUMBING <br />LINES, DRAIN LINES, AND ALL MECHANICAL ITEMS SHALL BE CAPPED AT <br />SOURCE AND REMOVED IN A MANNER TO MEET ALL LANDLORD AND CODE <br />REQUIREMENTS, UNLESS DIRECTED OTHERWISE. <br />E. GENERAL CONTRACTOR RESPONSIBILITIES <br />1. GENERAL CONTRACTOR IS -10 NOTIFY TENANT IMMEDIATELY OF ANY <br />SEVERE DISCREPANCIES OR IRREGULARITIES DISCOVERED DURING DEMOLITION <br />WHICH MIGHT AFFECT THE CURRENT STORE DESIGN. GENERAL CONTRACTOR <br />IS TO PAY SPECIAL ATTENTION TO AVAILABLE HEIGHT FOR INTENDED CEILING <br />ELEVATION, MECHANICAL DUCTWORK AND RECESSED LIGHTING. <br />2. GENERAL CONTRACTOR IS TO ERECT CONSTRUCTION BARRICADES AND <br />DEBRIS/DUCT SCREENS PER LANDLORD'S SPECIFICATIONS. CONTACT <br />LANDLORD'S REPRESENTATIVE PRIOR TO THE COMMENCEMENT OF ALL <br />DEMOLITION WORK. <br />3. GENERAL CONTRACTOR IS RESPONSIBLE FOR PATCHING, REPAIRING AND <br />LEVELING OF THE EXISTING FLOOR SLAB, REPAIR OF DEMISING WALLS AND <br />ROOF DECK AFTER COMPLETION OF ALL DEMOLITION AND PRIOR TO THE <br />COMMENCEMENT OF NEW CON STRUCTION.000RDINATE WITH LANDLORD <br />RESPONSIBILITY IN PERFORMING ANY AND ALL ROOF WORK. <br />DIVISION 03000 - CONCRETE <br />03300 CAST -IN -PLACE CONCRETE <br />PART 1 - GENERAL <br />A. PROVIDE_ AND INSTALL_ CONCRETE AS INDICATED ON THE DRAWINGS. <br />B. CONCRETE WORK SHALL CONFORM TO THE LATEST EDITION OF <br />"AMERICAN CONCRETE INSTITUTE" CODES AND STANDARDS INCLUDING ACI <br />301, ACI 315, AND ACI 318. <br />C. CONCRETE STRENGTHS ARE AS FOLLOWS- CLASS 13000 PSI INTERIOR <br />SLABS (OR MIN.REQUIRED PER LANDLORD SPECIFICATIONS.) <br />D. REINFORCEMENT (PER LANDLORD REQUIREMENTS) <br />E. BONDING AGENT (IF REQUIRED) <br />1. "SONOBOND" EPDXY CONCRETE BONDING AGENT OR EQUAL <br />a. MANUFACTURER: CHEMTREX, INC. <br />889 VALLEY PARK DRIVE <br />SHAKOPEE, MINNESOTA 55379-1854 <br />2. CONSULT MANUFACTURER FOR APPLICATION PROCEDURE. <br />ASTM C881 <br />F. VAPOR BARRIER <br />1. SLAB ON GRADES TO RECEIVE 6 MIL. CLEAR OR BLACK POLYETHYLENE <br />FILM WITH MINIMUMOF 12" OVERLAP. TAPE ALL SEAMS. <br />PART 2 - PREPARATION / EXECUTION <br />A. CONCRETE CONTRACTOR SHALL ASSUME FULL_ RESPONSIBILITY FOR <br />STRENGTH, CONSISTENCY PROPORTIONS AND HANDLING OF CONCRETE. <br />B. VERIFY THAT COMPACTED GRANULAR BASE IS IN PLACE AND READY TO <br />SUPPORT PAVING AND IMPOSED LOADS. <br />C. VERIFY GRADIENT AND ELEVATIONS OF BASE ARE CORRECT. THICKNESS <br />AND REINFORCING AS SHOWN ON DRAWINGS. <br />D. IMMEDIATELY AFTER PLACEMENT, PROTECT PAVEMENT FROM <br />MECHANICAL INJURY, <br />E. DEPOSIT CONCRETE WITHIN ANY ONE SECTION CONTINUOUSLY SO <br />THAT NO CONCRETE_ WILL BE PLACED ON OLDER CONCRETE WHICH HAS SET <br />SUFFICIENTLY TO RESULT IN SEAMS AND PLANES OF WEAKNESS WITHIN <br />SECTION. <br />F. PLACE SLABS FOR FULL THICKNESS IN ONE OPERATION, WITHOUT <br />CHANGES IN PROPERTIES; SCREED TO PROPER ELEVATION, FLOAT AND LIGHTLY <br />TROWEL. UNLESS OTHERWISE SPECIFIED, WHEN CONCRETE HAS SET <br />SUFFICIENTLY TO RING UNDER TROWEL, GIVE SLAB SECOND TROWELING TO <br />PRODUCE SMOOTH, DENSE SURFACE. DUSTING OF SURFACES WITH CEMENT I5 <br />PROHIBITED. <br />G. SUBGRADE MATERIAL USED: REMOVAL OF ALL ORGANIC MATERIAL. <br />COMPACT SUB GRADE_ FOR SLABS ON GRADE TO 95 CRUSHED GRAVEL <br />SUB -BASE AT ALL AREAS TO RECEIVE NEW CONCRETE. MIN. 6" OF MATERIAL. <br />RE -COMPACTION OF 95% OPTIMUM DENSITY. <br />H. FINISHES <br />1. GIVE TYPICAL INTERIOR FLOOR SLABS A STEEL TROWEL FINISH WITH <br />CLASS A TOLERANCE (TRUE PLANES WITHIN 1/8 IN 10 FT. AS DETERMINED BY A <br />10 FOOT STRAIGHTEDGE PLACED ANYWHERE ON SLAB IN ANY DIRECTION). <br />I. PROVIDE SAW CUT CONTROL JOINTS 1/8" WIDTH x 1" DEEP AT MAXIMUM <br />400 SQUARE FOOT AREA. <br />J. APPLY BONDING AGENT (AS SPECIFIED) TO ADJACENT CONCRETE <br />SURFACES IMMEDIATELY PRIOR TO PLACEMENT OF CONCRETE. <br />03732 CONCRETE REPAIR <br />PART 1 - GENERAL <br />A. THE EXTENT OF CONCRETE REPAIR WORK INCLUDES REMAINING FLOOR <br />AREAS AFTER DEMOLITION PROVIDING A LEVEL FLOOR THROUGHOUT TO <br />RECEIVE FUTURE FINISHES, AFTER DEMOLITION. <br />B. COMPLY WITH MANUFACTURER'S REQUIREMENTS FOR INSTALLATION OF <br />ITEMS AND FINISHES BY OTHER TRADES, INCLUDING THOSE ITEMS AND <br />FINISHES PROVIDED AND/OR INSTALLED BY TENANT. <br />C. FLOOR LEVELER CONCRETE TO BE INSTALLED AT LOW AREAS, HOLES <br />AND DEPRESSIONS. PATCH CRACKS AND BROKEN CONCRETE WITH FLOOR <br />PATCH TROWELED SMOOTH IN ACCORDANCE WITH MANUFACTURER'S <br />INSTRUCTIONS AND LANDLORD SPECIFICATIONS. UNDERLAYMENT <br />COMPOUND TO BE FREE FLOWING, SELF -LEVELING, PUMPABLE, AND <br />CEMENT -BASED FOR APPLICATIONS FROM ONE INCH THICK TO FEATHERED <br />EDGES. <br />PART 2 - PREPARATION / EXECUTION <br />A. CONCRETE REPAIR <br />1. DO NOT PROCEED WITH WORK UNTIL VISITING THE SITE AND <br />DETERMINING CONDITIONS TO DECIDE METHODS OF REPAIR. COORDINATE <br />WITH TENANT'S CONSTRUCTION MANAGER. <br />2. REMOVE AND DISPOSE OF EXISTING FLOOR FINISHES WHERE INDICATED <br />ON DEMOLITION PLAN. <br />3. THOROUGHLY CLEAN FLOOR SLAB REMOVING CONDITIONS THAT WILL <br />AFFECT BOND INCLUDING RESIDUE FROM REMOVAL OF ADHESIVES, <br />UNDERLAYMENTS, STAINS, OILS, ETC. <br />4. REMOVE HIGH FLOOR LEVELS AND LOOSE CONCRETE. <br />5. ROUGH IN CONCRETE IN AREAS WHERE PATCHING IS REQUIRED, SUCH <br />AS CRACKED, SPALLED, OR HOLES DUE TO REMOVAL OF EXISTING WORK. <br />6. GRIND HIGH SPOTS. <br />7. AT LOCATIONS OF CONSTRUCTION JOINTS IN EXISTING SLAB, CONTINUE <br />JOINTS THROUGH NEW FLOOR IN LEVELING AREA. SAW CUT JOINT OR PLACE <br />1/16" WIDE METAL BAR IN THE JOINT LOCATION COINCIDENT WITH EXISTING. <br />8. TRENCH ONLY AT SLAB ON GRADE. VERIFY AND GET APPROVAL_ OF <br />TRENCH OR CORE LOCATIONS WITH THE LANDLORDS REPRESENTATIVE AND <br />MALL STRUCTURE PRIOR TO COMPLETING ANY WORK. CORES TO BE SEALED <br />WATERPROOF. SEE SECT. 07200 "INSULATION AND WATERPROOFING" FOR <br />ADDITIONAL WATERPROOFING INFORMATION <br />CLEAN AREAS REMOVING ALL WASTE MATERIAL, BROOM CLEAN. <br />DIVISION 04000 - MASONRY <br />NO WORK UNDER THIS SECTION <br />DIVISION 05000 - METALS <br />05120 STRUCTURAL STEEL <br />PART 1 - GENERAL <br />A. PROVIDE ALL LABOR, MATERIAL AND EQUIPMENT NECESSARY FOR <br />COMPLETE INSTALLATION OF STEEL FRAMING AND SUPPORT MEMBERS, <br />ANGLES, PLATES, ANCHOR BOLTS REQUIRED FOR THE CONNECTION, SETTING <br />AND BEARING OF COMPLETE STRUCTURE AS SHOWN ON THE DRAWINGS OR <br />SPECIFIED HEREIN. <br />B. SEE STRUCTURAL DOCUMENTS FOR ADDITIONAL SPECIFICATIONS / <br />STANDARDS. <br />C. THE STRUCTURE IS DESIGNED TO BE SELF-SUPPORTING AND STABLE <br />AFTER THE PROJECT IS FULLY COMPLETED, IT IS THE CONTRACTOR'S SOLE <br />RESPONSIBILITY TO DETERMINE ERECTION PROCEDURE AND SEQUENCE AND <br />TO INSURE STABILITY OF THE BUILDING AND ITS COMPONENT PARTS AND <br />ADEQUACY OF TEMPORARY SUPPORT DURING ERECTION. THIS INCLUDES THE <br />ADDITION OF WHATEVER TEMPORARY BRACING, GUY OR TIE DOWNS MIGHT BE <br />NECESSARY. SUCH MATERIAL IS NOT SHOWN ON DRAWINGS. IF APPLIED, <br />THEY SHALL BE REMOVED AS CONDITIONS PERMIT AND SHALL REMAIN <br />CONTRACTOR'S PROPERTY. <br />D. PROVIDE OPENINGS AND SPECIAL FRAMING REQUIRED BY OTHER <br />TRADES. MECHANICAL FRAMING LOADS, OPENINGS, AND STRUCTURE RELATED <br />TO MECHANICAL REQUIREMENTS ARE SHOWN FOR BIDDING PURPOSES ONLY. <br />CONTRACTOR SHALL OBTAIN WRITTEN SIGN -OFF FROM MECHANICAL_ AND <br />OTHER TRADES FOR SPECIFIC REQUIREMENTS BEFORE PROCEEDING WITH SUCH <br />WORK. ARCHITECT'S OR ENGINEER'S APPROVAL OF ERECTION AND SHOP <br />DRAWINGS SHALL NOT RELIEVE CONTRACTOR FROM THIS RESPONSIBILITY. <br />E. VERIFY THE EXACT SIZE AND LOCATION OF ALL OPENINGS PRIOR TO <br />FABRICATION OF STEEL FRAMING MEMBERS, <br />F. SHOP DRAWINGS: SUBMIT STAMPED/SEAL SHOP DRAWINGS TO <br />ARCHITECT INDICATING SHOP AND ERECTION DETAILS, INCLUDING CUTS, <br />CONNECTIONS, HOLES, THREADED FASTENERS AND WELDS. <br />G. PRE -ASSEMBLE ITEMS IN SHOP TO GREATEST POSSIBLE EXTENT TO <br />MINIMIZE FIELD SPLICING AND ASSEMBLY. DISASSEMBLE UNITS ONLY AS <br />(NECESSARY FOR SHIPPING AND HANDLING LIMITATIONS. CLEARLY MARK UNITS <br />FOR RE -ASSEMBLY AND COORDINATE INSTALLATION <br />H. WELDING PROCEDURES, WELDERS, WELDING OPERATIONS AND TACKERS <br />SHALL BE QUALIFIED IN ACCORDANCE WITH AWS-D1.1- "STRUCTURAL <br />WELDING CODE". <br />I. "HOT WORK PERMIT" SHOULD BE PULLED AS NEEDED AND REQUIRED. HOT AND <br />WELDING WORK, SHOULD BE EXECUTED PER ILL. RULES AND REGULATIONS. <br />J. FABRICATOR SHALL BE A MEMBER OF AMERICAN INSTITUTE OF STEEL <br />CONSTRUCTION. <br />K. FABRICATE STRUCTURAL STEEL IN ACCORDANCE WITH RISC <br />"SPECIFICATIONS FOR DESIGN, FABRICATION AND ERECTION OF STRUCTURAL <br />STEEL FOR BUILDINGS" AND "CODE OF STANDARD PRACTICE". <br />1. UNLESS OTHERWISE SHOWN, FABRICATOR SHALL DESIGN / DETAIL <br />CONNECTIONS IN CONFORMANCE WITH AISC STANDARD FOR FORCES AND <br />MOMENTS SHOWN. <br />2. WHERE FASTENING SPACINGS OR SIZES ARE NOT SHOWN, CONTRACTOR <br />SHALL USE SPACINGS AND SIZES OF BOLTS, SCREWS, WELDS, ETC., WHICH WILL <br />DEVELOP THE FULL STRENGTH OF THE MEMBERS BEING FASTENED. THUS <br />FAILURE DUE TO OVER -STRESSING MUST OCCUR IN THE MEMBERS BEFORE <br />OCCURRING IN THE FASTENINGS. <br />PART 2 - PREPARATION / EXECUTION <br />A. PRE -ASSEMBLE ITEMS IN SHOP TO GREATEST POSSIBLE EXTENT TO <br />MINIMIZE FIELD SPLICING AND ASSEMBLY. DISASSEMBLE UNITS ONLY AS <br />NECESSARY FOR SHIPPING AND HANDLING LIMITATIONS. CLEARLY MARK UNITS <br />FOR RE -ASSEMBLY AND COORDINATE INSTALLATION. <br />B. SHOP CONNECTIONS SHALL BE WELDED. <br />C. FIELD CONNECTIONS: HIGH STRENGTH FASTENERS SHALL BE USED FOR <br />BOLTED CONNECTIONS. <br />1. STRUCTURAL STEEL FY 36 KSI STEEL, ASTM A36. <br />2. STRUCTURAL STEEL TUBING: FY 46 KSI COLD -FORMED TUBING EXCEPT <br />ROUND, ASTM A500-68, GRADE B. <br />3. STEEL PIPE: ASTM A53, GRADE B. <br />4. ANCHOR BOLT: CONFORM TO ASTM A307. <br />5. WELDING ELECTRODES: ASTM A233, E-70 OR BETTER. <br />6. HIGH STRENGTH THREADED FASTENERS: ASTM A325 OR A-490, <br />7. METAL STUDS: SIZE ACCORDING TO CONSTRUCTION DOCUMENTS x 20 <br />GAUGE STEEL AT 16" O.C. TRACKS TO BE ANCHORED BY MEDIUM POWER <br />ACTUATED FASTENERS @ 24" O.C. <br />8. EXTERIOR / INTERIOR METAL STUDS: SIZE ACCORDING TO <br />CONSTRUCTION DOCUMENTS X 25 GAUGE AT 16" O.C.. <br />9. SHOP PAINT PRIMER: STANDARD PRIMER: <br />a. SSPC PAINT 15 <br />b. TNEMEC 1009 GRAY METAL PRIMER <br />C. MARTIN-SENOUR CO. #664 RED OXIDE ZINC CHROMATE PRIMER <br />d. PRATT AND LAMBERT NOXIDE 107, ONE DAY PRIMER -GRAY. E. STEEL <br />SHALL BE CLEAN AND FREE FROM OIL, DIRT, LOOSE MILL SCALE AND ANY <br />OTHER SUBSTANCE THAT WOULD IMPAIR WELDING, PERFORMANCE OF <br />FRICTION -TYPE BOLTED. <br />81- <br />CONSTRUCTION <br />MANAGEMENT <br />.Y..._ _ _ <br />Construction for: <br />Revisions: <br />Mark Date <br />V� u <br />C 0 R T L A H 0 <br />M 0 R G A N 1 <br />A R C H I T E C T <br />L- -- - 1I <br />711 N. FIELDER RD. <br />ARLINGTON, TX 76012 <br />PH: (817) 635-5696 <br />FAX: (817) 635-5699 <br />Seal <br />Architect Job No.: <br />33N2022 <br />m2l_ <br />Nextore Store Resign Revision No.: <br />h <br />Nextore Project <br />Number 86841 <br />Brand Design Type: <br />PV 3.0 <br />ISSUED FOR: <br />® CONSTRUCTION <br />Tale <br />SPECIFICATIONS <br />1 OF 4 <br />Rate 04/19/2022 Sheet <br />Drawn 0y <br />STAFF 003 <br />Checked By - <br />C-m­ I_ <br />