Laserfiche WebLink
EVERETT PUBLIC WORKS DEPARTMENT  SMITH ISLAND ESTUARY RESTORATION YEARS 5 & 6 MONITORING <br />SCHEDULE <br />The project timeline has been developed in coordination with EPWD. All Year 5 and Year 6 work is <br />expected to occur between March 2023 and approximately the end of September 2024. <br />Table 2– Smith Island Estuary Restoration Years 5 and 6 Anticipated Schedule <br />SCHEDULE TASK TASK DESCRIPTION <br />Year 5 2023 <br />March-April Task 4 Wildlife use monitoring (spring) <br />May-July Task 1 Estuarine habitat delineation, hydrology, and salinity monitoring <br />August or early September Task 2 Wetland vegetation monitoring and drone image <br />Late September/October Tasks <br />3 & 4 Wildlife use monitoring; receive and compile fish data <br />October-December Task 5 Year 5 Monitoring Report <br />March through December Task 6 Client coordination and project management <br />Year 6 2024 <br />August or September Task 7 Year 6 site condition check; summary memo to EPWD <br />NTP 2023 through Contract <br />Period of Performance <br />Task 8 Additional Unanticipated Services <br />DocuSign Envelope ID: B75A46E0-B4A7-4C6C-B91E-69B691B92514