Table 1. Summary of project budget and schedule. Anticipated project duration is March 2023 through December 31, 2023. Blue shading indicates anticipated task duration, based on assumption of field work in Phase II also concluding (once contracted) by December 31, 2023. Task Subtotal 2023 Mar Apr May Jun Jul AugSep Oct NovDec1 Task 1: Evaluate and enhance existing COE crossing inventory $21,800 2 Task 2: Refine and conduct preliminary barrier prioritization $17,2883 Task 3: Meetings and project management $5,797 4 Task 4: Contingency $5,112 Total $49,997 Contract End: Dec 31, 2023