March 26, 2019 <br /> HWA Project No. 2015-061-21 Task 600-7 <br /> I We expect that supporting the sewer system with the proposed pile supported buildings will <br /> involve hanging the sewer line from the bottom of the proposed building floor slab or grade <br /> beams. To prevent differential settlements between pipes and utility structures, all required <br /> Imanholes and cleanouts should also be supported by the proposed pile supported buildings. We <br /> recommend that all sewer related elements be backfilled with pea gravel. This will allow the pea <br /> gravel to flow off or around the structural supported elements as the surrounding soils settle. A <br /> Iseparator fabric should be placed over the pea gravel wherever concrete is to be poured over the <br /> pea gravel or soil is to be placed over the pea gravel. The sewer system should continue to be <br /> pile supported between pile-supported buildings. Failure to maintain this pile support will result <br /> in significant differential settlement and potential system failures. <br /> We expect that the proposed sanitary sewer system, associated with the Phase 1 development, <br /> Iwill be grade supported from Lift Station 43 to the southern end of the proposed pile-supported <br /> buildings. Long term settlement is expected to occur across this distance. We recommend that <br /> I this segment of grade supported system be designed with an increased fall that will allow for <br /> proper function after as much as 30 inches of settlement occurs. Flexible connections should be <br /> constructed at the point that the proposed sewer transitions from grade-supported to pile- <br /> supported. <br /> 4.4.4 Storm Drain <br /> IWe expect that the storm drain system for Riverfront Boulevard will be constructed <br /> conventionally within the roadway. Therefore, the storm drain system is expected to undergo the <br /> I same deferential settlements as the roadway. As shown in Figure 5, our analysis indicates that <br /> several low areas along the roadway are expected to develop over time. To reduce future <br /> ponding along the roadway, we recommend that additional storm drain inlets be positioned at <br /> Ilocations where long-term settlements are expected to be greatest. Additionally, we recommend <br /> that the storm drain system be designed with sufficient fall to ensure that the system will function <br /> after as much as 30-inches of settlement occurs. <br /> 4.4.5 Utility Excavation Considerations <br /> I The near surface soils along the roadway alignment consist of varying amounts of fill soils over <br /> refuse. The fill soils consist of silty sands that were compacted to 90 percent of modified proctor <br /> at the time of placement. In some areas the fill soils possess increased sand content. Available <br /> Igeotechnical explorations indicate that the thickness of the fill soils vary along the road <br /> alignment from as much as 20 feet to as little as 2 feet in some areas. Fill thickness appears to be <br /> I greatest south of Station 30+00 and thin out north of Station 30+00. An 18-inch thick layer of <br /> cement treated soils should be expected within the near surface soils along portions of the <br /> roadway alignment. Landfill refuse exists below the fill at all locations along the roadway <br /> I alignment. Excavations through each of these material types may result in specific construction <br /> challenges. These challenges are addressed below. <br /> I <br /> Geotechnical Report Revision 3 26 2019.doc 15 HWA GEOSCIENCES INC. <br />