§ A.2.2 Unless otherwise provided,the Contract Time is the period of time,including authorized adjustments,allotted in <br /> the Contract Documents for Substantial Completion of the Work.The Contract Time shall be measured from the date of <br /> commencement of the Work. <br /> § A.2.3 Substantial Completion <br /> § A.2.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents,the Construction <br /> Manager shall achieve Substantial Completion of the entire Work: <br /> (Check one of the following boxes and complete the necessary information.) <br /> [(< »] Not later than« »(z< »)calendar days from the date of commencement of the Work. <br /> [« »] By the following date:i< <br /> § A.2.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents,if portions of the Work <br /> are to be completed prior to Substantial Completion of the entire Work,the Construction Manager shall achieve <br /> Substantial Completion of such portions by the following dates: <br /> Portion of Work Substantial Completion Date <br /> § A.2.3.3 If the Construction Manager fails to achieve Substantial Completion as provided in this Section A.2.3, <br /> liquidated damages shall be assessed as follows: <br /> Construction Manager understands that if it fails to achieve Substantial Completion by the Substantial Completion Date <br /> (as specified in the GMP Amendment),Owner will suffer damages that are difficult to determine and accurately specify. <br /> Construction Manager agrees that if it fails to achieve Substantial Completion by the Substantial Completion Date, <br /> Construction Manager shall pay Owner as liquidated damages for each calendar day <br /> that Substantial Completion extends beyond the relevant Substantial Completion Date. <br /> Any liquidated damages assessed pursuant to this Contract shall be in lieu of all monetary liability for any and all extra <br /> costs,losses,expenses,claims,penalties and any other damages,whether special or consequential,and of whatsoever <br /> nature incurred by Owner which are caused by any delay in achieving Substantial Completion or Final Completion, <br /> provided this limitation shall not apply to Construction Manager's duty to indemnify the Owner or to warrant <br /> Construction Manager's Work as provided in this Contract and shall not apply to any loss,damage,cost or liability <br /> incurred by Owner due to factors unrelated to Construction Manager's delay. <br /> ARTICLE A.3 INFORMATION UPON WHICH AMENDMENT IS BASED <br /> § A.3.1 The Guaranteed Maximum Price and Contract Time set forth in this Amendment are based on the Contract <br /> Documents and the following: <br /> § A.3.1.1 The following Supplementary and other Conditions of the Contract: <br /> Document Title Date Pages <br /> § A.3.1.2 The following Specifications: <br /> (Either list the Specifications here, or refer to an exhibit attached to this Amendment.) <br /> « » <br /> Section Title Date Pages <br /> § A.3.1.3 The following Drawings: <br /> (Either list the Drawings here, or refer to an exhibit attached to this Amendment.) <br /> <( >' <br /> AIA Document A133'- 2019 Exhibit A. Copyright O 1991, 2003, 2009, and 2019 by The American Institute of Architects. All rights reserved. <br /> The "American Institute of Architects," "AIA," the AIA Logo, and "AIA Contract Documents" are registered trademarks and may not be used 3 <br /> without permission. This draft was produced by AIA software at 14:22:51 ET on 09/16/2022 under Order No.2114304515 which expires on <br /> 03/23/2023, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents° Terms <br /> of Service. To report copyright violations, e-mail copyright@aia.org. (1131696201) <br /> User Notes: <br />