Laserfiche WebLink
r • <br /> Page 3 August 7,2019 <br /> Martin <br /> report borings as 50 blow count material. Settlement is not anticipated but providing a "belt <br /> and suspenders" small VE's is for considerations during single day duration initial lift. <br /> Confirming, the soil nails are designed for all building uniform D + L + S loading plus the line <br /> load of the building exterior wall including tributary loading. The VE piles bear on dense <br /> glacial soils and are used for initial lift only. Vertical VE is continuously supported in its minor <br /> axis direction with lean mix grout plus soils. No lagging is used. For 50 ksi steel, axial <br /> capacity of 28 ksi x 5.62 in2 = 784 »41 kips is based on its major axis buckling capacity per <br /> AISC Table 4-22 with KL/rx= 30 (based on K= 2.1, initial lift L= 5 ft, rx=4.14.) Axial <br /> capacity is adequate, Flexural Capacity is adequate and combined stress is adequate per <br /> AISC Section H.1. See attached supplemental calculations. <br /> b) Pile Cap Plate: Please reference Detail 6/SS4.0 for the top of VE pile detail below the <br /> existing building. The piles are used to mitigate differential considerations. It is anticipated <br /> that the 50 plus blow count soils will continue to provide continuous support of the existing <br /> building between the VE piles. <br /> c) Footing and Pile support: Existing soils between the piles are to remain in place, <br /> supporting the existing building. It is anticipated that the 50 plus blow count soils will provide <br /> continuous support of the existing building between the VE piles. Shoring monitoring at the <br /> existing building is set to a tighter control than typical. RE monitoring notes on Sheet SS1.0. <br /> d) Pile Cap Detail: As noted in response to Item 7b) above, please reference Detail 6/SS4.0 for <br /> 3/4"thick x pile size cap plate. Calculations for maximum tributary loading of 41 kips, for pile <br /> bearing and pile side friction were previously submitted. Re Figure 3. RE attached <br /> supplemental shoring calculations confirming that the cap plate detail is acceptable. Again, <br /> please note that it is anticipated that the 50 plus blow count soils will provide continuous <br /> support of the existing building between the VE piles. The design of the partial depth VE piles <br /> in the very dense soils has been reviewed and OK'd by the geotechnical engineer. <br /> 8) ASD design VS Strength Design for wall flexural capacity: Reference response to Item 6) for <br /> soil nail system design using ASD allowed per FHWA NHl 14-007 Section 5.3.1 and Table 5.1. <br /> a) FHWA Table 5.1 ASD Factors of Safety: Confirming again, the previously submitted <br /> calculations meet or exceed all required ASD factors of safety RE. Table 5.1, following FHWA <br /> ASD design procedures and are acceptable without revision. <br /> b) Facing Reinforcement: The previously submitted ASD calculations are based on the WWF <br /> specified in the shoring drawings and are adequate. No additional calculations regarding <br /> reinforcement are required. <br /> Please call if you have any additional questions. <br /> Sincerely, /7/1"- <br /> , <br /> --All ff,i A, <br /> Anne McAteer-Brown, P.E., S.E. <br /> CC: Jeff Oaklief, Johnson Oaklief <br /> Matt Miller, AES Geo <br /> F ia7. <br /> ffrz'fs. <br /> _Lr • <br /> II f y f <br /> 34840 <,^ �! n <br />