1 <br /> City of Everett 00 72 00 - 50 <br /> 12.4.4 Inefficiencies <br /> 12.4.4.1 Adjustment of Contract Sum <br /> To the extent Contractor is entitled to an increase in Contract Sum because of inefficiencies or impaired <br /> productivity,then compensation due,if any,shall be calculated as provided in 9.5.ADJUSTMENT OF <br /> CONTRACT SUM. There is no entitlement to increase in Contract Sum for inefficiencies related to a <br /> Third Party or to a Force Majeure Event. <br /> 12.4.4.2 Adjustment of Contract Time <br /> To the extent Contractor is entitled to an extension of Contract Time because of inefficiencies or impaired <br /> productivity,then the time extension,if any,shall be determined as provided in 5.2.2.2 Extensions of <br /> Contract Time. <br /> 13. DISPUTES <br /> 13.1 RESOLUTION ' <br /> When a Dispute occurs during a Contract,the Contractor shall pursue resolution through the Owner's <br /> Representative. The Contractor shall follow the procedure stated in 12.CONTRACT CLAIMS herein <br /> and 5.2.2.2 Extensions of Contract Time for issues regarding the schedule and Contract Time. Timely <br /> and adequate Notice is a condition precedent to a Contract Claim. Timely and complete submission of a <br /> Contract Claim is a condition precedent to any entitlement by the Contractor to an adjustment of Contract <br /> Sum or Contract Time. Unless waived by the Owner,mediation is a condition precedent to the filing of <br /> any lawsuit,action or proceeding that seeks to recover on a Contract Claim,whether in whole or in part. <br /> 13.2 CONTINUING THE WORK <br /> Contractor shall carry on the Work and adhere to the schedule during all disputes or disagreements with <br /> Owner.No Work shall be delayed or postponed pending resolution of Disputes or disagreements,except <br /> as permitted by paragraph 15.04 or as Owner and Contractor may otherwise agree in writing. <br /> 14. TIME LIMITATIONS AND JURISDICTION <br /> The parties intend that all Claims and Disputes be dealt with promptly and expeditiously when they arise. <br /> The parties intend that all Claims and Disputes be resolved quickly and expeditiously and desire to avoid <br /> claims and Disputes that relate back to events or Work occurring months before. The parties desire to <br /> avoid litigation and the costs and expense of Claims and Disputes at the end of the Project. <br /> Any Contract Claim for adjustment of Contract Sum or Contract Time,or any Dispute or Contract Claim <br /> of any kind whatsoever,must be submitted,if at all,to the Owner or Owner's Representative no later than <br /> thirty(30)days after Notice was first required to be given by the Contractor as provided in ARTICLE <br /> 10.NOTICE TO OWNER. Failure to submit a Contract Claim within the thirty(30)days of the date <br /> Notice was required pursuant to ARTICLE 10.NOTICE TO OWNER constitutes a complete waiver of <br /> and bar to the Contract Claim,and Contractor is estopped from later asserting a Contract Claim or seeking <br /> any relief or remedy relating to the Dispute for which it failed to submit a Claim. <br /> Contractor may not sue,cross-claim,claim,or bring any action of any kind whatsoever against the Owner <br /> on any Contract Claim or Dispute after the expiration of one hundred eighty(180)days from Physical <br /> Completion. <br /> Any alleged cause of action by Owner or Contractor as to any acts or failures to act occurring prior to <br /> Substantial Completion shall be deemed to have accrued in any and all events not later than such date of <br /> Substantial Completion. I <br /> 1 <br /> 00 72 00 - 50 GENERAL CONDITIONS <br />