I <br /> City of Everett Inductive Charging Infrastructure for Field Installation 01 29 73 - 3 <br /> I 1. Distribute Contractor's office overhead and profit proportionally among allocated cost <br /> for each work activity. <br /> 2. Costs associated with ongoing mobilization activities can be listed separately or <br /> distributed evenly among allocated cost for each work activity. <br /> I 3. Assign overhead costs corresponding to start and finish dates for each work related <br /> activity. <br /> 4. Pro-rate associated work expenses related to work activities, including supervision, <br /> I temporary utilities, and small tools, over total Contract Time. <br /> 5. Assign directly related costs, including bonds, insurance, and schedules, to <br /> appropriate work activities. <br /> I 6. Claims for additional cost for storage of materials off-site are not accepted as a basis <br /> for monetary claims, except where need for off-site storage arose after the Bid and <br /> at request of the Owner. <br /> I C. Overhead and Administrative Costs: Distribute major cost items which are not a direct cost <br /> of actual work-in-place as line item in schedule of values, or distributed as general <br /> overhead expense. <br /> I1. Conditions of the Contract for Construction and Mobilization: Maximum 3 percent of <br /> Contract Sum. <br /> 2. Demobilization: Maximum 1 percent of Contract Sum. <br /> I <br /> 3. Commissioning of Operational Systems: See paragraph G for required 1% of HVAC <br /> Contract to be itemized on the Schedule of Values. <br /> 4. Closeout: Minimum of 1 percent of Contract Sum to cover closeout submittals and <br /> I documentation and 1 percent of contract sum to cover punchlist identification and <br /> completion. <br /> 5. See Paragraph E and F for required 1 percent of Contract Sum for Project Record <br /> I Documents completion and 1 percent for Operations and Maintenance Manuals <br /> completion. <br /> D. Stored Items: For materials not yet installed, for which Progress Payments are requested, <br /> I <br /> no payment for materials stored offsite will be made without prior notice to and acceptance <br /> by Owner. <br /> I 1. Submit clear title to ownership of materials in writing to Owner. <br /> 2. Support initial value with proof of purchase invoices. <br /> 3. Include value-added costs as separate line item when subsequently delivered to site <br /> I and installed. <br /> 4. Differentiate between items stored on-site and items stored off-site. <br /> 5. Provide acceptable proof of insurance and bonding of storage facility and contents. <br /> 6. Store materials no greater distance than 50 miles from Project site. <br /> I 7. Make storage facilities available and open to Owner and Architect observation. <br /> 8. Store materials for which payments are requested in separate areas away from <br /> other materials and clearly marked or labeled to identify name of Owner, Project, <br /> Iand Contractor. <br /> E. Project Record Documents: Include line item of at least 1 percent of Contract Sum for <br /> I <br /> preparation, maintenance, and duplication. Upon completion, a portion of this amount will <br /> be released based upon percentage of completion of the Work as a whole. <br /> I01 29 73- 3 SCHEDULE OF VALUES <br /> I <br />