City of Everett 00 7200 - 31 <br />2024 WPCF Biosolids Removal UT 3826-2 <br /> <br /> <br />00 7200 - 31 GENERAL CONDITIONS <br />In special circumstances where a particular item of equipment is placed in continuous service before <br />Substantial Completion of all the Work, the correction period for that item may start to run from an earlier <br />date if so provided in the Specifications. <br />Where defective Work (and damage to other Work resulting there from) has been corrected or removed <br />and replaced under this Paragraph 8.10, the correction period hereunder with respect to such Work will be <br />extended for an additional period of one year after such correction or removal and replacement has been <br />satisfactorily completed. <br />Contractor’s obligations under this Paragraph 8.10 are in addition to any other obligation, guarantee or <br />warranty. The provisions of this Paragraph 8.10 shall not be construed as a substitute for or a waiver of <br />the provisions of any applicable statute of limitation or repose. <br />9. MEASUREMENT AND PAYMENT <br />9.1. PAYMENTS TO CONTRACTOR <br />9.1.1. Schedule of Values <br />The Contractor shall submit a Schedule of Values at least fifteen (15) days prior to submitting its first <br />Application for Payment. If the Project contains Unit Price Work, in whole or in part, then the Schedule <br />of Values for that portion of the Work shall also be based on unit prices. If the Bid form calls for a lump <br />sum price, in whole or in part, then the Schedule of Values shall: reasonably allocate the Contract Sum <br />among the various portions of the Work; be complete; be organized to include detailed breakdown of each <br />major unit of the Work; be organized to correspond to Contractor’s schedule; break down the Contract <br />Sum showing the value assigned to each part of the Work; include an allowance for profit and Overhead; <br />include Unit Price Work, if and to the extent indicated on the Bid form; be so organized as to facilitate <br />assessment of work and payment of Subcontractors; and be balanced. To the greatest extent possible, the <br />breakdown shall use the same tasks or units as the Contractor’s schedule. Contractor shall provide <br />documentation substantiating the cost allocation if asked by the Owner’s Representative. Upon <br />acceptance of the Schedule of Values by the Owner’s Representative, it shall be used as a basis for all <br />requests for payment. <br />9.1.2. Progress Payments <br />9.1.2.1 Payment Request Procedures: <br />By the tenth day of each month, or by schedule mutually agreed upon in writing by the Contractor and <br />Owner’s Representative, the Contractor shall submit to the Owner’s Representative a partial payment <br />estimate filled out and signed by the Contractor covering acceptable Work performed during the previous <br />month, or since the last partial payment estimate was submitted. Contractor’s submission of a progress <br />pay estimate constitutes a material representation by the Contractor that it performed all of the Work <br />described in the progress pay estimate during the relevant time period in a workmanlike manner and that <br />the materials for which payment is requested reasonably conform to the Specifications and are either on <br />the job Site or have been installed. If requested by the Owner’s Representative, the Contractor shall <br />provide such additional data as may be reasonably required to support the payment estimate. Such data <br />may include satisfactory evidence of payment for Equipment, materials and labor including payments to <br />Subcontractors and Suppliers. Certified invoices by the Suppliers shall accompany a request for payment <br />for delivered Equipment and material. Such Equipment and material shall be suitably and safely stored at <br />the Site of the Work. Payment requests shall summarize accepted operating and maintenance material <br />with request for Equipment payment. A progress payment is preliminary only. By making a progress <br />payment, the Owner does not waive or release its right, nor is it estopped from asserting, that previous <br />progress payments were not earned or were in error, whether in whole or in part. <br />9.1.2.2 Review Procedures: <br />The Owner’s Representative will review the estimate and either indicate in writing to the Owner his or <br />her concurrence with the estimate and his or her recommendation that payment be made, or indicate in