2024 Pavement Maintenance Overlay SPECIAL PROVISIONS PW# 3823 32 schedule format. Regardless of which format used, the schedule shall identify the critical 1 path. The Engineer will evaluate the Type A Progress Schedule and approve or return the 2 schedule for corrections within 15 calendar days of receiving the submittal. 3 4 5 1-08.4.RTF 6 1-08.4 Prosecution of Work 7 8 Delete this section and replace it with the following: 9 10 1-08.4 Notice to Proceed and Prosecution of Work 11 (July 23, 2015 APWA GSP) 12 13 Notice to Proceed will be given after the contract has been executed and the contract 14 bond and evidence of insurance have been approved and filed by the Contracting 15 Agency. The Contractor shall not commence with the work until the Notice to Proceed 16 has been given by the Engineer. The Contractor shall commence construction activities 17 on the project site within ten days of the Notice to Proceed Date, unless otherwise 18 approved in writing. The Contractor shall diligently pursue the work to the physical 19 completion date within the time specified in the contract. Voluntary shutdown or slowing 20 of operations by the Contractor shall not relieve the Contractor of the responsibility to 21 complete the work within the time(s) specified in the contract. 22 23 When shown in the Plans, the first order of work shall be the installation of high visibility 24 fencing to delineate all areas for protection or restoration, as described in the Contract. 25 Installation of high visibility fencing adjacent to the roadway shall occur after the 26 placement of all necessary signs and traffic control devices in accordance with 1-10.1(2). 27 Upon construction of the fencing, the Contractor shall request the Engineer to inspect the 28 fence. No other work shall be performed on the site until the Contracting Agency has 29 accepted the installation of high visibility fencing, as described in the Contract. 30 31 1-08.5.OptionA.RTF 32 1-08.5 Time for Completion 33 (December 30, 2022 APWA GSP, Option A) 34 35 36 Revise the third and fourth paragraphs to read: 37 38 Contract time shall begin on the first working day following the Notice to Proceed Date. 39 40 Each working day shall be charged to the contract as it occurs, until the contract work is 41 physically complete. If substantial completion has been granted and all the authorized 42 working days have been used, charging of working days will cease. Each week the 43 Engineer will provide the Contractor a statement that shows the number of working days: 44 (1) charged to the contract the week before; (2) specified for the physical completion of 45 the contract; and (3) remaining for the physical completion of the contract. The statement 46 will also show the nonworking days and all partial or whole days the Engineer declares 47 as unworkable The statement will be identified as a Written Determination by the 48 Engineer. If the Contractor does not agree with the Written Determination of working 49 days, the Contractor shall pursue the protest procedures in accordance with Section 1-50 04.5. By failing to follow the procedures of Section 1-04.5, the Contractor shall be 51 deemed as having accepted the statement as correct. If the Contractor is approved to 52