Laserfiche WebLink
CITY OF EVERETT SPECIAL PROVISIONS <br /> <br />Water Main Replacement “Y” – Ph 1 Div 1 – GENERAL REQMTS March 2024 <br />Work Order No. UP 3814 SP-134 <br />1-09.11A(2) Extra Work <br />1-09.11A(2)A Adjustment of Contract Sum <br />If the Contractor is entitled to an adjustment of Contract Sum because of Extra <br />Work, the adjustment shall be calculated and paid as provided in 1-09.4 <br />EQUITABLE ADJUSTMENT. This amount includes jobsite and home office <br />Overheads for such Work, including any schedule delays relating to such Work. <br />Therefore, no compensation in addition to that provided in 1-09.6 FORCE <br />ACCOUNT shall be paid for such things as Extended Overhead or other costs or <br />damages. <br />1-09.11A(2)B Extension of Contract Time <br />Extensions of Contract Time caused by Extra Work shall be determined as <br />provided in 1-08.3 PROGRESS SCHEDULE and 1-08.8 EXTENSIONS OF TIME. <br />1-09.11A(3) Delays <br />1-09.11A(3)A City Caused Delay Unrelated to Extra Work <br />1-09.11A(3)A1 Adjustment of Contract Sum <br />If the Contractor is entitled to an adjustment of Contract Sum because of a <br />Delay solely caused by the City that does not relate to Extra Work, Contractor <br />shall only be compensated for the items below, less all funds paid pursuant to <br />any change in the Contract Sum that contributed to the Delay: <br />1. Documented, incurred cost of nonproductive field supervision or <br />labor extended because of the Delay; <br />2. Documented, incurred cost of home office supervision to attend <br />jobsite meetings; <br />3. Documented, incurred cost of temporary facilities or equipment <br />rental extended because of the Delay; <br />4. Documented, incurred cost of insurance extended because of the <br />Delay; <br />5. General and administrative overhead in an amount to be agreed <br />upon, but not to exceed three percent of original Contract Sum <br />divided by the Contract Time for each day of the Delay. <br />City shall not owe Contractor compensation for Extended Overhead or other <br />delay costs to the extent Contractor or anyone other than the City contributed <br />to or is concurrently responsible for the Delay. <br />1-09.11A(3)A2 Adjustment of Contract Time <br />If the Contractor is entitled to an adjustment of Contract Time because of a <br />Delay solely caused by the City that does not relate to Extra Work, Contractor <br />shall be entitled to an adjustment of Contract Time to the extent the Delay <br />increases the duration of the Project, as measured by the critical path and as <br />demonstrated pursuant to the requirements of 1-08.8 EXTENSIONS OF <br />TIME. <br />1-09.11A(3)B Contractor Caused Delay <br />If the Contractor is solely responsible for any Delay to any interim milestone, <br />Substantial Completion, Physical Completion, or the Completion Date, the City <br />shall be entitled to liquidated or other damages as provided elsewhere in the <br />Contract Documents. The Contractor accepts the risk of any Delays caused by <br />strikes, work slowdowns, job actions and labor unrest of any kind. Contractor shall <br />not be entitled to any increase in Contract Sum or Contract Time due to a Delay it <br />caused.