My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
Earthworks Solutions, LLC 5/3/2024
>
Contracts
>
Capital Contract
>
Capital Construction Contracts and Change Orders
>
Earthworks Solutions, LLC 5/3/2024
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
5/3/2024 1:19:59 PM
Creation date
5/3/2024 8:46:58 AM
Metadata
Fields
Template:
Contracts
Contractor's Name
Earthworks Solutions, LLC
Approval Date
5/3/2024
Council Approval Date
5/8/2024
Department
Public Works
Department Project Manager
Amie Roshak
Subject / Project Title
Water Main Replacement "Y"
Tracking Number
0004333
Total Compensation
$3,300,935.68
Contract Type
Capital Contract
Contract Subtype
Capital Construction Contracts and Change Orders
Retention Period
10 Years Then Transfer to State Archivist
Imported from EPIC
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
385
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
Download electronic document
View images
View plain text
CITY OF EVERETT SPECIAL PROVISIONS <br /> <br />Water Main Replacement “Y” – Ph 1 Div 1 – GENERAL REQMTS March 2024 <br />Work Order No. UP 3814 SP-134 <br />1-09.11A(2) Extra Work <br />1-09.11A(2)A Adjustment of Contract Sum <br />If the Contractor is entitled to an adjustment of Contract Sum because of Extra <br />Work, the adjustment shall be calculated and paid as provided in 1-09.4 <br />EQUITABLE ADJUSTMENT. This amount includes jobsite and home office <br />Overheads for such Work, including any schedule delays relating to such Work. <br />Therefore, no compensation in addition to that provided in 1-09.6 FORCE <br />ACCOUNT shall be paid for such things as Extended Overhead or other costs or <br />damages. <br />1-09.11A(2)B Extension of Contract Time <br />Extensions of Contract Time caused by Extra Work shall be determined as <br />provided in 1-08.3 PROGRESS SCHEDULE and 1-08.8 EXTENSIONS OF TIME. <br />1-09.11A(3) Delays <br />1-09.11A(3)A City Caused Delay Unrelated to Extra Work <br />1-09.11A(3)A1 Adjustment of Contract Sum <br />If the Contractor is entitled to an adjustment of Contract Sum because of a <br />Delay solely caused by the City that does not relate to Extra Work, Contractor <br />shall only be compensated for the items below, less all funds paid pursuant to <br />any change in the Contract Sum that contributed to the Delay: <br />1. Documented, incurred cost of nonproductive field supervision or <br />labor extended because of the Delay; <br />2. Documented, incurred cost of home office supervision to attend <br />jobsite meetings; <br />3. Documented, incurred cost of temporary facilities or equipment <br />rental extended because of the Delay; <br />4. Documented, incurred cost of insurance extended because of the <br />Delay; <br />5. General and administrative overhead in an amount to be agreed <br />upon, but not to exceed three percent of original Contract Sum <br />divided by the Contract Time for each day of the Delay. <br />City shall not owe Contractor compensation for Extended Overhead or other <br />delay costs to the extent Contractor or anyone other than the City contributed <br />to or is concurrently responsible for the Delay. <br />1-09.11A(3)A2 Adjustment of Contract Time <br />If the Contractor is entitled to an adjustment of Contract Time because of a <br />Delay solely caused by the City that does not relate to Extra Work, Contractor <br />shall be entitled to an adjustment of Contract Time to the extent the Delay <br />increases the duration of the Project, as measured by the critical path and as <br />demonstrated pursuant to the requirements of 1-08.8 EXTENSIONS OF <br />TIME. <br />1-09.11A(3)B Contractor Caused Delay <br />If the Contractor is solely responsible for any Delay to any interim milestone, <br />Substantial Completion, Physical Completion, or the Completion Date, the City <br />shall be entitled to liquidated or other damages as provided elsewhere in the <br />Contract Documents. The Contractor accepts the risk of any Delays caused by <br />strikes, work slowdowns, job actions and labor unrest of any kind. Contractor shall <br />not be entitled to any increase in Contract Sum or Contract Time due to a Delay it <br />caused.
The URL can be used to link to this page
Your browser does not support the video tag.