Laserfiche WebLink
City of Everett 00 7200 - 16 <br /> <br /> <br />General Conditions <br />007200-16 202082-10 May 2024 <br />pw://Carollo/Documents/WA/Everett/202082-100000/04 Design/04 Specs/Carollo/007200 (FS-100) <br /> <br />4.5. OWNER-CONTRACTOR COORDINATION <br />4.5.1. Service of Notice <br />Contractor agrees that any Notice, order, direction, request or other communication by the <br />Owner’s Representative or Owner to the Contractor shall be deemed received by the Contractor <br />if left at any office used by the Contractor or delivered to any of the Contractor’s officers, clerks <br />or employees or posted at the site of the Work or mailed to any post office addressed to the <br />Contractor at the address given in the Contract Documents or mailed to the Contractor's last <br />known place of business. If mailed, any form of communication will be deemed to have been <br />given to and received by the Contractor the day after the day of mailing. <br />4.5.2. Suggestions to Contractor <br />Nothing in these Contract Documents requires the Owner’s Representative to provide the <br />Contractor with direction or advice on how to do the Work, construction practices, or means and <br />methods. If the Owner’s Representative approves, suggests or recommends any construction <br />practice, means, method or manner for doing the Work or producing materials, the approval or <br />recommendation shall not: (A) guarantee that following the method or manner will result in <br />compliance with the Contract Documents; (B) relieve the Contractor of any risks or obligations <br />under the Contract Documents; or (C) create any liability by the Owner to the Contractor. <br />Suggestions as to the plans or methods of accomplishing the Work or Contract requirements by <br />the Owner or the Owner’s Representative to the Contractor but not specified or required, if <br />adopted or followed by the Contractor in whole or in part, shall be used at the risk and <br />responsibility of the Contractor. The Owner and the Owner’s Representative assume no <br />responsibility therefore and in no way will be held liable for any defects in the Work which may <br />result from or be caused by use of such plan or method or Work. <br />4.5.3 Meetings with Owner <br />The Contractor shall have its duly authorized representative attend periodic informational <br />meetings with the Owner’s Representative and City staff, as reasonably required by the Owner. <br />Contractor, Owner, and Owner’s Representative shall meet as often as determined by the <br />Owner’s Representative, but no less often than once each month. The purpose of the meeting is <br />to review Project status in relation to the construction schedule; review value of Work completed <br />during the previous month; and, if applicable, review Contractor's plans to return Project status <br />to that required by the schedule. If requested by the Owner or Owner’s Representative, the <br />Contractor shall submit a written progress report within five (5) days following this meeting, <br />comprising: <br />1. The current construction schedule indicating percent complete, actual completion or start <br />dates since the previous review, the estimated remaining duration for each activity in <br />progress, Schedule of Values update, and narrative summary. <br />2. Reasons any activities are behind schedule and the corrective steps being taken. <br /> 4.5.4. Cooperation with Others <br />The Contractor agrees to permit entry to the Site of the Work by the Owner, its employees or <br />other contractors performing work on behalf of the Owner. The Contractor shall afford to the <br />Owner, other contractors and their employees, reasonable facilities and cooperation and shall <br />arrange its work and dispose of its materials in such a manner as to not interfere with the <br />activities of the Owner or of others upon the Site of Work. The Contractor shall promptly make <br />good any Contractor-caused injury or damage to persons or property that may be sustained by