Laserfiche WebLink
City of Everett 00 72 00 - 45 <br /> <br /> <br /> <br />00 72 00 - 45 GENERAL CONDITIONS <br />v. Overhead (general and administrative). <br />vi. Subcontractor’s contract claims (in the same level of detail as specified herein is <br />required for all Subcontractor’s contract claims); and <br />vii. Other categories as specified by the Contractor or the Owner. <br />10. A notarized statement shall be submitted to the Owner's Representative containing the following <br />language: <br />Under the penalty of law for perjury or falsification, the undersigned, <br /> <br />______________________________, ______________________________ <br /> (name) (title) <br />of ____________________________________________________________ <br /> (company) <br />hereby certifies that the Contract Claim for an adjustment of the Contract Sum and/or <br />Contract Time, if any, made herein for Work on this Contract is a true and complete <br />statement of the factual basis of the Contract Claim and all actual costs incurred and time <br />sought, and is fully documented and supported under the Contract between the parties. <br />Date________________________________/s/ _______________________ <br />Subscribed and sworn before me this ____________ day of _______ <br />Notary Public <br />My Commission Expires: ___________________________________________ <br />12.3 FALSE OR OMITTED INFORMATION <br />The Contractor waives each Contract Claim for which it presents material information that it knows, or in <br />the exercise of reasonable care should know, is false, or omits or fails to disclose material information <br />relating to such Contract Claim. In such case, Contractor shall reimburse the Owner for any and all fees <br />and expenses incurred in investigating any such Contract Claim. <br />12.4 REMEDIES <br />12.4.1 General <br />If a Contract Claim has merit in whole or in part, then Contractor’s sole remedies shall be those provided <br />in this subsection. Contractor must timely and strictly comply with the requirements of 10. NOTICE TO <br />OWNER, 11. DIFFERING SITE CONDITIONS, 12. CONTRACT CLAIMS and all other General <br />Conditions relating to the Contract Claim. Adjustments to Contract Time shall be determined pursuant to <br />5.2.2.2 Extensions of Contract Time. Failure to comply strictly and timely shall be deemed a waiver of <br />the Contract Claim. <br />12.4.2 Extra Work <br />12.4.2.1 Adjustment of Contract Sum <br />If the Contractor is entitled to an adjustment of Contract Sum because of Extra Work, the adjustment shall <br />be calculated and paid as provided in 9.5. ADJUSTMENT OF CONTRACT SUM. This amount <br />includes jobsite and home office Overheads for such Work, including any schedule delays relating to such <br />Work. Therefore, no compensation in addition to that provided in 9.6. FORCE ACCOUNT shall be <br />paid for such things as extended Overhead or other costs or damages.