CITY OF EVERETT SPECIAL PROVISIONS <br /> <br /> <br /> <br /> <br /> Division 1 <br />Everett Mall Bus Platform General Requirements December 2024 <br />WO No – MALLSTN/24462 SP-51 <br />If the Contractor fails to provide the above notification within 60 calendar days, then the <br />Contractor shall yield to the City sole and exclusive discretion to allow all or part of the <br />claim on behalf of the Contractor, and the Contractor shall be deemed to have WAIVED <br />any and all defenses, objections, or other avoidances to the City’s allowance of the <br />claim, or the amount allowed by the City, under common law, constitution, statute, or the <br />Contract and these Standard Specifications. If all or part of a claim is allowed, the City <br />will notify the Contractor via certified mail that it has allowed all or part of the claim and <br />make appropriate payments to the claimant(s) with City funds. <br />Payments of funds by the City to claimant(s) under this Section will be made on behalf of <br />the Contractor and at the expense of the Contractor, and the Contractor shall be <br />unconditionally obligated to reimburse the City for the “total reimbursement amount”, <br />which is the sum of the amount paid to the claimant(s), plus all costs incurred by the City <br />in evaluating the circumstances surrounding the claim, the allowance of the claim, the <br />amount due to the claimant, and all other direct costs for the City’s administration and <br />payment of the claim on the Contractor’s behalf. The City will be authorized to withhold <br />the total reimbursement amount from amounts due the Contractor, or, if no further <br />payments are to be made to the Contractor under the Contract, the Contractor shall <br />directly reimburse the City for the amounts paid within 30 days of the date notice that the <br />claim was allowed was sent to the Contractor. In the event reimbursement from the <br />Contractor is not received by the City within 30 days, interest shall accrue on the total <br />reimbursement amount owing at the rate of 12 percent per annum calculated at a daily <br />rate from the date the Contractor was notified that the claim was allowed. The City’s <br />costs to enforce recovery of these amounts are additive to the amounts owing. <br />The Contractor specifically assumes all potential liability for actions brought by <br />employees of the Contractor and, solely for the purpose of enforcing the defense and <br />indemnification obligations set forth in 1-07.14, the Contractor specifically waives any <br />immunity granted under the State industrial insurance law, Title 51 RCW. This waiver <br />has been mutually negotiated by the parties. The Contractor shall similarly require that <br />each Subcontractor it retains in connection with the project comply with the terms of this <br />paragraph, waive any immunity granted under Title 51 RCW, and assume all liability for <br />actions brought by employees of the Subcontractor. <br />The indemnity, defense and other obligations in this 1-07.14 are in addition to any <br />indemnity, defense or other obligation that may be contained elsewhere in the Contract <br />Documents. <br />1-07.17 Utilities and Similar Facilities <br />Supplement 1-07.17 by adding the following: <br />The Contractor shall review its responsibilities under Chapter 19.122 RCW, a law <br />relating to underground utilities. Cost to the Contractor incurred as a result of complying <br />with this law shall be at the Contractor's expense. In accordance with RCW 19.122, the <br />Contractor shall call the Utility Coordinating Council One Call Center, 1-800-424-5555, <br />for field location, not less than 2 nor more than 10 business days before the scheduled <br />date for commencement of excavation that may affect underground utility facilities, <br />unless otherwise agreed upon by the parties involved. A business day is defined as any <br />day other than Saturday, Sunday, or a legal local, State, or Federal holiday. <br />The Contractor shall be responsible for determining the exact location, including service <br />connections, of all public and private underground utilities marked at the site of the <br />Work. The Contractor shall perform field verification prior to beginning Work that could <br />result in damage to buried utilities, including but not limited to exploratory excavations, in