My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
Colacurcio Brothers, Inc. 2/26/2025
>
Contracts
>
10 Years Then Transfer to State Archivist
>
2025
>
Colacurcio Brothers, Inc. 2/26/2025
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
3/12/2025 4:09:29 PM
Creation date
3/12/2025 3:44:09 PM
Metadata
Fields
Template:
Contracts
Contractor's Name
Colacurcio Brothers, Inc.
Approval Date
2/26/2025
Council Approval Date
3/12/2025
End Date
9/9/2025
Department
Transit
Department Project Manager
Brad Chenoweth
Subject / Project Title
Everett Mall Bus Platform
Tracking Number
0004733
Total Compensation
$1,992,715.50
Contract Type
Capital Contract
Contract Subtype
Capital Construction Contracts and Change Orders
Retention Period
10 Years Then Transfer to State Archivist
Imported from EPIC
No
Jump to thumbnail
< previous set
next set >
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
1121
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
Download electronic document
View images
View plain text
CITY OF EVERETT SPECIAL PROVISIONS <br /> <br /> <br /> <br /> <br /> Division 1 <br />Everett Mall Bus Platform General Requirements December 2024 <br />WO No – MALLSTN/24462 SP-93 <br />The Contractor shall be entitled to an extension of Contract Time for Delays to the extent <br />caused by COVID-19 Requirements. Extension of Contract Time shall be determined <br />pursuant to 1-08.8 EXTENSIONS OF TIME. This Contract Time extension is the <br />Contractor’s sole remedy if the Contract Time in the Contract Documents is insufficient <br />to complete the Work because of Baseline COVID-19 Requirements. <br />All other Contract Claims regarding COVID-19 are governed by Section 1-09.11A(3)D1 <br />CAUSED SOLELY BY THIRD PARTIES OR FORCE MAJEURE, including 4 without <br />limitation Contract Claims relating to unavailable or delayed labor, materials, equipment <br />or subcontractors to the extent caused by COVID-19. <br />Supplement Section 1-09 by adding the following: <br />1-09.11A Remedies <br />(*****) <br />1-09.11A(1) General <br />If a Contract Claim has merit in whole or in part, then Contractor’s sole remedies <br />shall be those provided in this subsection. Contractor shall timely and strictly comply <br />with the requirements of 1-04.5 NOTICE BY THE CONTRACTOR and 1-09.11(2) <br />CONTRACT CLAIMS and all other Contract Documents relating to the Contract <br />Claim. Adjustments to Contract Time shall be determined pursuant to 1-08.3 <br />PROGRESS SCHEDULE and 1-08.8 EXTENSIONS OF TIME. Failure to comply <br />strictly and timely shall be deemed a waiver of the Contract Claim. <br />1-09.11A(2) Extra Work <br />1-09.11A(2)A Adjustment of Contract Sum <br />If the Contractor is entitled to an adjustment of Contract Sum because of Extra <br />Work, the adjustment shall be calculated and paid as provided in 1-09.4 <br />EQUITABLE ADJUSTMENT. This amount includes jobsite and home office <br />Overheads for such Work, including any schedule delays relating to such Work. <br />Therefore, no compensation in addition to that provided in 1-09.6 FORCE <br />ACCOUNT shall be paid for such things as Extended Overhead or other costs or <br />damages. <br />1-09.11A(2)B Extension of Contract Time <br />Extensions of Contract Time caused by Extra Work shall be determined as <br />provided in 1-08.3 PROGRESS SCHEDULE and 1-08.8 EXTENSIONS OF <br />TIME. <br />1-09.11A(3) Delays <br />1-09.11A(3)A City Caused Delay Unrelated to Extra Work <br />1-09.11A(3)A1 Adjustment of Contract Sum <br />If the Contractor is entitled to an adjustment of Contract Sum because of a <br />Delay solely caused by the City that does not relate to Extra Work, Contractor <br />shall only be compensated for the items below, less all funds paid pursuant to <br />any change in the Contract Sum that contributed to the Delay: <br />1. Documented, incurred cost of nonproductive field supervision or labor <br />extended because of the Delay; <br />2. Documented, incurred cost of home office supervision to attend jobsite <br />meetings;
The URL can be used to link to this page
Your browser does not support the video tag.