Laserfiche WebLink
4 of 8 <br /> Wednesday, November 30, 2022 <br /> SCOPEOF WORK FOUNDATION SPECIALIST <br /> Crew will install 3" Helical Piles, as well as 3" Concentric Piers, and lift home to maximum practical recovery. Crew will drive <br /> piles to a maximum 25'after there will be a $20 a foot charge per pile. Crew will remove and replace concrete. <br /> L120 is in concurrence with pile layout recommended by R&R provided that the proposed layout is followed as marked and that a maximum pile <br /> spacing of 6'-Vo.c.and 8'-Vo.c.as noted on the level survey,is achieved. <br /> NOTES: <br /> 1. It is acceptable to install piles at the spacing shown with±0'-6"tolerance to allow for unexpected obstructions encountered during pile installation <br /> provided that no two adjacent spans exceed the spacing limitation of 6'-0"o.c and 8'-0"o.c.. <br /> 2. End piles are to be placed as close to corners as possible and shall not exceed a maximum corner distance of 3'-0"as marked. <br /> 3. Helical pile caps will be placed on helical piles 3 and 4. <br /> LEVEL SURVEY <br /> 3' 12' <br /> 31 0 -1/8 <br /> I <br /> 0 <br /> T � <br /> 3' - <br /> -1/4 <br /> 13' F = Existing Post <br /> -3/8 -1/2 = 3" Helical Pile <br /> = 3" Concentric Pier <br /> ❑ =Polyurethane Lift <br /> -5/8 -7/8 -7/8 <br /> LOCATE PILES -5/8 <br /> UNDER -1 3/8 <br /> EXISTING <br /> ED POST Ui _ 10 <br /> Cf)) 1 w <br /> -374 <br /> N <br /> LO TE -1 3/4 <br /> X HE AL PILE r CirQ <br /> PS UNDER 1 1/2 to - 9 <br /> 2 EXISTING 3 BN <br /> 6 POST -1 1/2 <br /> O <br /> 1 -1 LOCATE PILE WITHIN 2F MAX OF (4)PILES @ 6'-0"O.C.MAX <br /> CORNER - 8 <br /> LOCATE PILE <br /> W rack WITHIN 4FT MAX Y <br /> w U U LOCATE PILE WITHIN <br /> a - 2-1 2 coOF CORNER —1 FT MAX OF <br /> (� -2 1/4 C3/ -3 5/8 _ CORNER <br /> N - j �T <br /> 3 4 28' 5 <br /> f—(4)PILES @ 6'-0"O.C. MAX <br /> NOTE:L120's scope is limited to the perimeter support systems/continuous footings of the primary structure.All stabilization and replacement efforts of <br /> exterior decks and deck supporting elements are outside of L120's contract and scope and are not addressed in this package. -L120 <br />