MASONRY OBSERVATIONS REPORT <br />MAYES lferracon <br />Report Number: M7231404.0009 <br />Service Date: 07/12/23 <br />Report Date: 07/13/23 <br />Client <br />Brixton Everett LLC <br />Attn: Kyle Godat <br />120 S Sierra Ave <br />Solana Beach, CA 92075 <br />Permit No.: B2208-032 <br />20225 Cedar Valley Rd Ste 110 <br />Lynnwood, WA 98036-6365 <br />425-742-9360 <br />Project <br />Everett Mall Redevelopment <br />1402 SE Everett Mall Way <br />Everett, WA <br />Project Number: M7231404 <br />General Information <br />Bayley Construction requested Mayes Terracon be on site for observation of grout and reinforcing steel for the walls, which <br />are being constructed by R & D Masonry. Mayes Terracon representative arrived on site at 1200 and departed at 1600. <br />The construction documents referenced for this inspection include the structural drawings <br />Reinforcing Steel Observations <br />Construction <br />Elevation / <br />Vertical Bond Beam <br />Lintel <br />Embedded Status <br />Comments <br />Type <br />Location <br />Reinforcement Reinforcement <br />Reinforcement <br />Items <br />Summary Summary <br />Summary <br />Walls <br />2nd 4' lift to top <br />Verified for bar N/A <br />N/A <br />To be installed at a Complies Anchors for canopy to be drilled in <br />of walls / <br />sizes and grade, <br />later date, but end <br />later. Contractor did layout work <br />canopy CMU <br />clearance, <br />and cross cells <br />prior to grouting for avoidance to <br />support walls. <br />spacing, lap and <br />removed for grout. <br />miss reinforcing steel bars. <br />cell cleanliness. <br />Vertical bar positioners were not utilized. Referenced documents S2.01 and 10/S3.01. <br />Grout Observations <br />Construction <br />Masonry <br />Elevation / Location <br />Grout <br />Cleanouts Consolidation <br />Production Methods Status <br />Type <br />Type <br />Technique <br />Provided Method <br />Walls <br />CMU <br />2nd 4' final wall lift / canopy <br />Low Lift <br />N/A Vibration <br />Smokey Point grout Complies <br />CMU support walls. <br />mix PG65030 <br />Cast (1) set of (3) fully grouted CMU masonry. Please reference grout compressive strength report M7231404.-0009A. <br />The results of observation(s) for today were reported to Bayley Construction. <br />Compliance Statement <br />Based on our observations, masonry activities observed at the above -referenced locations appeared to be completed in <br />general accordance with the project plans and specifications. <br />Services: Special Inspections / Materials Testing <br />Mayes/Terracon Rep.: Todd Wirtz <br />Reported To: Bayley Construction <br />Contractor: Bayley Construction <br />Report Distribution: <br />(1) Brixton Everett LLC, Kyle Godat (1) Bayley Construction, Tony Betz <br />(1) City of Everett WA, Permit Services (1) Mayes Testing Engineers, Inc, <br />(1) Mayes Testing Engineers, Inc, Mike Donna Pollard <br />Mattox <br />Reviewed By: '_. V_ )_.___ <br />�/ Barry Tuttle <br />Project Field Manager <br />The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client indicated above <br />and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable to the actual samples tested at <br />the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical materials. <br />D11014, 04-29-22 Rev.5 Page 1 of 1 <br />