Install Footings <br /> Design footings to comply with the following additional requirements: <br /> • To keep footings directly under I-beams and other support points, size them <br /> slightly larger than the minimum required area to allow slight adjustment of the <br /> pier location during home installation. <br /> • Design footings with a footing extension (projection beyond the base of the <br /> pier) no greater than the footing thickness(Figure 11). Increase footing thick- <br /> ness if necessary. <br /> — Figure 11.Maximum footing <br /> extensions <br /> 4' e' 16'BLOCK <br /> 4': 4' f <br /> TYP 1 24' <br /> FOOTING EXTENDS BY I w f tr I NO <br /> YES EXTENDS BY ITS N."'' MORE THAN ITS 24' _4 I wA' ' 4 <br /> THICKNESS OR THICKNESS <br /> LESS --. YES 45 <br /> 4' r 4`1_4: <br /> J I <br /> SPLIT FOOTING SPLIT FOOTING <br /> YES EXTENDS LESS NO EXTENDS MORE <br /> THAN ONE THIRD THAN ONE THIRD <br /> ITS WIDTH ITS WIDTH <br /> • The footing sizes shown are for square pads and are based on the surface ar- <br /> ea (square inches) Design non-square footings such that the area and thick- <br /> ness is equal to or greater than the area of the square footing shown in Table <br /> 10 and the distance from the edge of the pier to the edge of the footing is not <br /> more than the thickness of the footing. <br /> TABLE 10A.FOOTER THICKNESS <br /> Poured in Place Footing for Poured in Place Footing for `'`\��'P�ttIN 1 %/ ` <br /> Single Stack Pier Double Stack Pier `\,` G 8;C` xi, <br /> Footer Max Footer Footer I Max Footer �, .•`• •R ��GY''. <br /> Thickness Dimension Max.Area Max.Area `+ <br /> Thickness Dimension r. <br /> (in) (in x in) (sq.in) (in) (in x in) (by.in) .. * ta. �`•.� <br /> .. :Cr AGR1CU 'Ula •6 28 x 20 560 6 28 x 28 784 ,• ( 'o ` l y <br /> 8 32 x 24 768 8 32 x 32 1024 ... S <br /> 10 36 x 28 1008 10 36 x 36 1296 r :`.'1✓ ME in.,..in.r.. .i.:. <br /> 12 40 x 32 1280 12 40 x 40 1600 r/ •'. s. <br /> .0 01 (}g .•• Ca`ct\�� <br /> 14 44 x 44 1936 I/ `'.- OF YEN-\` <br /> 16 48 x 48 2304 <br /> STEP 6. INSTALL FOOTINGS <br /> Construct the footings as follows <br /> • Maintain the distance between adjacent piers to within 10°' of the tabulated '/ii\V"Z <br /> spacing and so the average distance between piers is equal to or less than the Placing Concrete anchors. <br /> tabulated spacing. If anchors will be placed in <br /> • Whenever possible. place pier supports directly under the required locations. If concrete follow instructions <br /> plumbing. electrical or mechanical equipment interferes, place supports no in Install Stabilizing Sys- <br /> more than 6 inches in either direction of the support point. tern (p.74)to determine <br /> • Recess perimeter pier supports no more than 10 inches from the edge of the anchor layout. Either place <br /> floor with added support as shown in Figure 12. anchors immediately after <br /> the concrete has been <br /> poured or drill them in after <br /> the concrete has set. <br />